3 - 1
【
Chapter 3
Dismantle and installation instruction
】
3-1.
Dismantle instruction:
1. Installation tools required:
(1) Crane.
(2) Scissors
(3) Wrench (17 / 19 mm)
(4) Adjustable wrench.
(5) Ladder.
(6) Claw hammer.
(7) Air wrench. (21 mm)
(8) Hammer.
2. Uncrating:
(1) Pry off the clips around the top of the crate with a claw hammer and remove
the top panel. Some crates have lag screws which hold the crate walls and
roof together. A wrench is necessary to remove these.
(2) Pry off the enforcement beam where inside the craft’s top. (It should be pried
by two people.)
(3) Pry off all but one clip at each corner of the crate.
(4) Remove plastic cover.
3. Uncrating the pallet:
(1) Unbolt the 6 fixed bolts and caps where on the pallet by wrench or
adjustable wrench.
(2) Cut off the iron plate, which fixed the accessories on the pallet, and remove
the accessories by crane.
4. Move the machine without the crate: Move the machine by crane or forklifter.
(1) The capability of forklifter is stated as previous chapter, The forks must be
over 1800 mm (at least over 100mm from machine’s center)
(2) When moving by forklifter, it has to move slowly and pay attention on
balance.
(3) Please use suitable slings and steel frames to lift the machine.
(4) Please remove the machine from the pallet by crane or forklifter.
(5) The notices are same as Section 2-2.
5. Inspection:
Our machine passes the strict function test and quality test before shipping. The
customer shall check the follows items after uncrating:
(1) Whether or not the model is correct (coincidence with order)?
(2) Whether or not the accessories or parts are complete?
(3) Whether or not the machine was damaged due to transportation?
(4) Whether or not the machine includes the inspection record?