1�  Inspect the panel for any damage and any components that may have loosened during shipping� Control panel must be installed a 

minimum of 5ft (3m in Canada) from the inside wall of the pond, unless separated from the body of water by a fence, wall, or other 

permanent barrier that will make the unit inaccessible to persons in the water� Install the control panel to a post structure, side of a 

building, or other reliable means. This structure must support the panel and prevent movement/flexing of the panel. Use #10 x 1” 

or longer screws in the mounting points of the control panel to secure to the post structure� NOTE: The control panel must be hung 

upright to be waterproof� It is also advised to mount the panel out of direct sunlight if possible by mounting the panel in a North 

direction. Also, mount the panel above the potential flood plain to prevent water entry during a possible flood event.

2� 

Set timer in the control panel to desired ON and OFF times per the instructions for each specific timer.

3.  Follow all local and national electrical codes for this installation and consult a qualified electrician or service person if needed.

• 

(For 120V Installations) Plug the aerator cord into the C-25 outlet labeled “UNIT”. If lights are included, plug the transformer 

cord into the C-25 outlet labeled “LIGHT”. Now you are ready to plug the C-25 into the 120V power supply on the post and 

ENJOY YOUR NEW KASCO AERATOR!

• 

(For 240V Installations–3400H, 4400H) All electrical connections to this panel must be made with proper strain relief cord grip 

fittings or with conduit connections as required by local and national electric codes. The bottom of the enclosure is reserved 

for field installation of these connections.

• 

C85 / C95 non-metallic control panel: Incoming power connection: (Power feed) This control panel requires a 240V or 208V -4 

wire service (L1, L2, N, & G) and must be fed with a power circuit protected by a circuit breaker or a fused disconnect switch 

to provide circuit protection and a disconnection means. C-85 panel requires at least a 30amp protected circuit feeding the 

panel. C-95 panel requires at least a 40-amp protected circuit feeding the panel. Connect your power feed as detailed in the 

wiring diagram provided with this panel. L1 connects to Terminal #1, L2 connects to Terminal #2, N connects to Terminal N, G 

connects to Terminal GROUND -located on chassis plate� Be sure to provide adequately sized power conductors to prevent 

excessive voltage drop� Consult with your electrician to properly size power feed conductors� Use copper conductors only� 

Aerator power cord connection: Your aerator (pump) will be provided with a flexible power cord for connection to this control 

panel� If the power cord has a plug, you will need to cut it off� The power cord conductors (black, white, green) will need to be 

stripped back 1/2”. The outer black jacket should be stripped back at least 3 inches. Follow the connection diagram for termi

-

nating these three wires to the terminal blocks in the control panel. Black connects to Terminal #4,White connects to Terminal 

#5, Green connects to Terminal G.

•  This control panel requires a hardwire connection for the light kit(s)� To connect the light kit(s), you will need to cut off the 

power cord plug that is molded to the light kit power cord� Strip back the black outer jacket of the light kit power cord at least 

3inches to reveal the three internal wires of the power cord. (Black, white, and green conductors). These three wires will need 

to be stripped back 1/2”. Follow the connection diagram for terminating these three wires to the terminal blocks in the control 

panel. Light kit connections: Black connects to Terminal #6, White connects to Terminal #7, Green connects to Terminal G.

4.  Test the GFCB with the test button now and every 30 days. Lights can now be installed per Instructions included with the lights. 

Once completed, power can be restored to the panel� Record the following data while the Aerator is operating in the water under 

load:

L1-L2 

  Volts 

 

 L1 

  Amps

L1-N 

  Volts 

 

 L2 

  Amps

L2-N 

  Volts 

 

Any unauthorized modifications to this control panel will void the UL listing and the Kasco warranty.

Date installed:

 

    / 

 

/

Back to Contents

Summary of Contents for 2400VFX

Page 1: ...FX Decorative Aerator 2400VFX 3400VFX 3400HVFX 4400VFX 4400HVFX 800 Deere Rd Prescott WI 54021 715 262 4488 sales kascomarine com www kascomarine com Document number 884170 Operation Maintenance Manua...

Page 2: ...rd to either side of the float If you have a light kit make sure that the unit cord is tied to one side of the float and the light cord to the other for balance It is extremely important to test the G...

Page 3: ...conductor and or a grounding type attachment plug To reduce the risk of electrical shock be certain the unit is properly connected to the Kasco supplied control panel refer to the instructions include...

Page 4: ...210 4 1 4 split washers 7 840537 5 1 4 3 4 OD flat washer 10 251300 6 1 4 20 x 1 3 4 hex head screw 3 475630 7 Bottom screen section 3 361540 8 1 4 20 nut 3 840536 9 8 nut 6 771034 10 8 flat washer 12...

Page 5: ...with legs 2 Lock washer goes between bolt and flat washer Tighten down in 4 places 3 4 5 9 10 11 12 10 3 Turn over Bring bottom screen sections together 8 4 5 5 6 ASSEMBLY INSTRUCTIONS 4 Tighten down...

Page 6: ...by sinking them further below the surface UNIT INSTALLATION INSTRUCTIONS After unit is installed in the water connect the power cord to a properly installed Kasco control panel C 85 C 95 etc with buil...

Page 7: ...onnect switch to provide circuit protection and a disconnection means C 85 panel requires at least a 30amp protected circuit feeding the panel C 95 panel requires at least a 40 amp protected circuit f...

Page 8: ...n the ON position 2 If the GFCI tests okay restore power by pushing the RESET button back in THE RESET BUTTON MUST BE PUSHED FIRMLY AND FULLY INTO PLACE UNTIL IT LOCKS AND REMAINS DEPRESSED AFTER PRES...

Page 9: ...ippers to the outer ring position for the entire period that the aerator is to be turned ON i e 15min for each tripper on the 24 hour dial When the tripper is pushed to the inside the switch is in the...

Page 10: ...50 5A Prop 2400VFX 1 240595 5B Prop 3400VFX 3400HVFX 1 340595 5C Prop 4400VFX 4400HVFX 1 440600 6A Top disk 2400VFX 1 241025 6B Top disk 3400VFX 3400HVFX 1 241035 6C Top disk 4400VFX 4400HVFX 1 241045...

Page 11: ...unit upside down if it will sit for a long period of time to ensure continued oil lubrication of seals units that sit upright for many months or years have a greater likelihood of seals drying out CLE...

Page 12: ...riginal receipt and registering the equipment online at kascomarine com under the Warranty Information section Once warranty coverage has been established the unit may be sent to Kasco Marine or any K...

Page 13: ...t before the work is performed All estimates that are rejected for repair will be destroyed unless otherwise directed by the customer Rejected equipment can be returned at the customer s expense for s...

Page 14: ...aker single phase units only Each Kasco aerator has a Thermal Overload built in that will turn the unit off when it overheats Once the unit has cooled down it will start back up If you are noticing th...

Page 15: ...customer to ship and pay freight to Kasco Note Contact Information should be that of the person or company to contact for repair information Company name Contact name First name Last name Address Str...

Reviews: