24
5.2.1
Mounting the control unit
The control unit must be mounted to an even wall in the immediate vicinity of the radiation chamber.
The mounting plates included in the delivery allow for flexible mounting to the
wall.
See Chap. 4.4.2 for the dimensions of the control unit
Decide which way you want to install the mounting
plates.
Aligning the control unit
Mounting plate
lengthwise
Mounting plate crosswise
Securing the mounting plate
Fig. 7: Aligning the mounting plates
Fig. 8: Aligning the control unit
Do not install the control unit below dripping pipes and make sure that the
display is at eye level (approx. 1600-1800 mm).
If a lot of condensation occurs at the installation site, use a suitable
dehumidifier.
The control unit can be mounted at any 90° degree angle to the wall. To ensure that the control unit can be
used, the housing cover with the control panel must be adapted accordingly (see Fig. 8).