SECTION 6 – GENERAL SPECIFICATIONS & OPERATOR MAINTENANCE
6-28
– JLG Lift –
31210162
6.10 TILT SENSOR VERIFICATION
Interval - At least every 6 month of operation.
1.
Drive the machine on a known level surface.
2.
Chock both rear wheels.
3.
Remove chassis hoods and place a spirit level (digital
display) on the chassis positioned in line w/chassis.
4.
Using a jack of appropriate capacity, lift the front on the
chassis. The tilt alarm must be activated within 0.2°
below the value in Table 6-1.
5.
Place the spirit level perpendicular to the chassis and lift
either the left or the right side of the chassis. The tilt
alarm must be activated within 0.2° below the value in
Table 6-1.
6.
If the tilt warning is not activated within the indicated
angle values, the tilt sensor must be recalibrated by a
qualified technician before replacing machine into ser-
vice.
Figure 6-17. Jacking Points
Summary of Contents for Toucan 12E
Page 2: ......
Page 12: ...TABLE OF CONTENTS vi JLG Lift 31210162 NOTES...
Page 22: ...SECTION 1 SAFETY PRECAUTIONS 1 10 JLG Lift 31210162 NOTES...
Page 54: ...SECTION 3 MACHINE CONTROLS AND INDICATORS 3 20 JLG Lift 31210162 NOTES...
Page 58: ...SECTION 4 MACHINE OPERATION 4 4 JLG Lift 31210162 Figure 4 3 Grade and Side Slope...
Page 74: ...SECTION 4 MACHINE OPERATION 4 20 JLG Lift 31210162 NOTES...
Page 135: ......