6
Reattach cabinet bottom cover.
Fitting the extension wings
Fit the left and right table extension
wings (A and E) as well as the rear
table extension.
Bolt two support arms (B) onto each
table extension.
Mounting the measuring scale
Bolt both scales (A, B, Fig 3) to the
front of the table/ extensions.
Fig 3
The scales are numbered form zero
outwards.
Mounting the handles
Mount the +/– crank handle on the
front and the 0°/45° crank handle on
the side.
Machine stand assembly
Assemble the legs (A, Fig 4) and
horizontal beams (B, C) as shown.
Fig 4
Mounting machine to stand
Place the machine on top of the
machine stand and connect together
with 4 hex cap bolts and washers
(Fig 5).
Fig 5
Now it is time to align the extension
tables to be flat with the machine
table.
(You can use the rip fence profile as
gauge).
Mounting of sawblade
see chapter 7.1
Mounting of raving knife
see chapter 7.2
Mounting of table insert
Secure the table insert in place with
8 screws (Fig 6).
Fig 6
Mounting of saw guard
see chapter 7.3
Mounting of rip fence
see chapter 7.5
Mounting of push stick rest
Mount the 2 push stick hooks (A, B,
Fig 7) with 4 pan head screws.
Fig 7
5.3 Dust connection
Before initial operation, the machine
must be connected to a dust
extractor. The suction should switch
on automatically when the saw is
switched on.
Attach the connecting hose (A, Fig 8)
and the Y-piece (B) as shown.
Fig 8
A 57mm or 100mm dust collector
can be connected.
5.4 Mains connection
Mains connection and any extension
cords used must comply with
applicable regulations.
The mains voltage must comply with
the information on the machine
licence plate.
The mains connection must have a
16A surge-proof fuse.
Only use connection cables marked
H07RN-F
Connections and repairs to the
electrical equipment may only be
carried out by qualified electricians.
5.5 Starting operation
You can start the machine with the
green on button. The red button on
the main switch (A, Fig 9) stops the
machine.
Fig 9
In case of machine overload the
motor overload cut-off (B) will react.
After appr.10 min of cooling the
machine can be started again.
Push in the overload cut-off.