MAGBEAST HM200T
12 |
P a g e
[11] CIRCUIT & CONNECTION WIRINGDIAGRAM
1.
CIRCUIT
WARNING - THIS APPLIANCE MUST BE EARTHED!
Insulation Resistance Test
With the magnet switch in the ON position, apply a voltage of 1.5kv between the live
connection on the mains plug and the frame of the machine for a duration of 7 seconds.
The reading obtained should not fall below infinity. Should a fault be indicated, it
must be
found and rectified
.
[12] GIB ADJUSTMENT
1. New Sliding System: Machines have a very advanced and stable sliding system. It
consists of three main parts: Slide Board, Precisely Ground Bar &Adjustment Gib.
It has a very wear-resistant structure and keeps first condition as time goes on. It
helps to cut comparatively bigger holes easier than normal dove-tail system without
any bad movement in sliding area.
2. Gib Adjustment: Adjust the Gib using side bolts loose or tight, if necessary.