3.4.
Installation of the awnings frame
CAUTION!
Installation of awning or adjustment can be made only by trained installation team.
The installation must be in accordance with the requirements of safety, particular in health and safety
regulations. Use scaffolding or ladders that are in good condition. If the awning is not installed on the ground
floor but on the upper floors, it is recommended to mark up and protect the area below. Do not make
changes in the structure of the awning.
3.5.
Qualifications of the installation team
●
Observe safety rules.
●
Ability to use of ladders and scaffolds.
●
Ensure transport and storage of the awning.
●
Experience in the use of tools and equipment.
●
Appropriate certificate of approval and use for fixing materials in construction.
●
Installation training at Dragon company (recommended).
●
Training the end user before using the awning.
●
Pass manuals and warranty on the end-user.
Note
Installation of the awning, adaptation and check the proper functioning can only be
done by trained installers team. This team is responsible for the right installation (with
the anchor bolts) readjustment and test run of the awning.
3.6.
Fastening and pulling on the ropes
If you need to pull the awning in a higher level with the aid of ropes must one:
●
Take out from the packaging.
●
Transport ropes must be fastened so that the awning can not slip out.
●
Uniform load distribution (in horizontal position) during the pulling out.
3.7.
Required tools
●
Ladders / Scaffold,
●
Level,
●
Ropes,
●
Measuring tape,
●
Impact drill and drill bit (depending on the substrate),
●
Imbus (3mm, 5mm, 6mm),
●
Wrench / ringspanner (SW10),
●
Socket wrench, extended (SW13),
●
Tools for the chosen installation method (type of anchor, etc).