Filler unit (Optional)
• Set the control valve lever (1) to turn off
the flow.
• Pour 50 liters of water in the sprayer’s
tank.
• Remove the return hose (2) from the con-
trol valve.
• Connect the filler unit hose (3) to the con-
trol valve in the place of the return hose.
• Put the filler unit (4) in the clean water
source and the end of its discharge hose
(5) into the tank filling opening.
• Run the sprayer with 540 rpm at the PTO.
ATENÇÃO!
Em caso de formulação pó-molhável, desligue a bomba somente após o término da
calda do tanque, a fim de evitar a decantação do produto.
ATTENTION!
The sprayer filling operation must be done in places appropriate for this purpose or
through appropriate vehicles (trucks, trailers, etc.).
Never collect water from rivers, lakes, dams, streams, brooks, etc. by using the
sprayer’s return system.