SHUTDOWN AND CLEANING (STEAM-HEATED MODELS):
At the end of the workday, place the power switch in the OFF
position, secure the flow of steam to the machine and open the door(s). Open the drain valves and allow the machine to drain
completely. Remove the pawl bar assembly (clean as required). Remove the pan strainers and, if equipped, the prewash strain-
ers, run off sheets and scrap basket strainer. Remove the wash and, if equipped, the prewash arms and verify that the nozzles
and arms are free from obstructions. Flush the arms with fresh water. Remove the pump suction strainers and clean out as
required. Remove the rinse tray assembly and clean. Remove the curtains and scrub with a mild detergent and warm water.
Wipe out the inside of the unit and then reassemble with the components previously removed.
SHUTDOWN AND CLEANING (GAS-HEATED MODELS):
At the end of the work day, shut down the gas booster in accor-
dance with manufacturer’s instructions. Place the power switch in the OFF position, secure the flow to the machine and open
the door(s). Open the drain valves and allow the machine to drain completely. Remove the pawl bar assembly (clean as
required). Remove the pan strainers and, if equipped, the prewash strainers, run off sheets and scrap basket strainer. Remove
the wash and, if equipped, the prewash arms and verify that the nozzles and arms are free from obstructions. Flush the arms
with fresh water. Remove the pump suction strainers and clean out as required. Remove the rinse tray assembly and clean.
Remove the curtains and scrub with a mild detergent and warm water. Wipe out the inside of the unit and then reassemble with
the components previously removed.
SECTION 2: INSTALLATION/OPERATION INSTRUCTIONS
DISHMACHINE OPERATION INSTRUCTIONS (CONTINUED)
41
Summary of Contents for AJ-64CE
Page 9: ...1 SECTION 1 SPECIFICATION INFORMATION...
Page 37: ...29 SECTION 2 INSTALLATION OPERATION INSTRUCTIONS...
Page 52: ...44 SECTION 3 PREVENTATIVE MAINTENANCE...
Page 57: ...49 SECTION 4 TROUBLESHOOTING SECTION...
Page 61: ...53 SECTION 5 PARTS SECTION...
Page 121: ...113 SECTION 6 ELECTRICAL SCHEMATICS...
Page 122: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CE 208 230 VOLT 60 HZ SINGLE PHASE PRIMARY SIDE 114...
Page 123: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CE 208 230 VOLT 60 HZ SINGLE PHASE SECONDARY SIDE 115...
Page 124: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CE 208 230 VOLT 60 HZ THREE PHASE PRIMARY SIDE 116...
Page 125: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CE 208 230 VOLT 60 HZ THREE PHASE SECONDARY SIDE 117...
Page 126: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CE 460 VOLT 60 HZ THREE PHASE PRIMARY SIDE 118...
Page 128: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CS 208 230 VOLT 60 HZ SINGLE PHASE PRIMARY SIDE 120...
Page 130: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CS 208 230 VOLT 60 HZ THREE PHASE PRIMARY SIDE 122...
Page 131: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CS 208 230 VOLT 60 HZ THREE PHASE SECONDARY SIDE 123...
Page 132: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CS 460 VOLT 60 HZ THREE PHASE PRIMARY SIDE 124...
Page 133: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 64CS 460 VOLT 60 HZ THREE PHASE SECONDARY SIDE 125...
Page 138: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 86CE AJ 100CE 460 VOLT 60 HZ THREE PHASE PRIMARY SIDE 130...
Page 139: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 86CE AJ 100CE 460 VOLT 60 HZ THREE PHASE SECONDARY SIDE 131...
Page 144: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 86CS AJ 100CS 460 VOLT 60 HZ THREE PHASE PRIMARY SIDE 136...
Page 145: ...SECTION 6 ELECTRICAL SCHEMATICS AJ 86CS AJ 100CS 460 VOLT 60 HZ THREE PHASE SECONDARY SIDE 137...
Page 152: ...SECTION 6 ELECTRICAL SCHEMATICS CONVEYOR EXHAUST FAN HOOKUP 144...
Page 154: ......