7 UNPACKING AND PLACING
At all times, machine is sent after being
meticulously tested in our factory and confirmed
they are fully operational.
Manufacturer company is not responsible of
the damages occurred during transportation.
7.1
Remove the package after the machine arrives
and make sure that none of the pieces were
damaged during transportation. If any damages
are determined, do not install the machine and
notify authorized technical service.
7.2
Use proper equipment to avoid damaging the
machine while removing the package.
7.3
All packages (plastic, polyurethane materials,
woods, nails, etc.) are dangerous and should be
kept away from children.
9.2
Position of the machine should be compatible
with general installation. Foundation should be
flat and tiling should not be damaged by the
weight of the machine.
9.3
Make sure the machine is positioned in the
right way for maintenance. Place the machine on
the balance by using screwed feet. Image 5.
Warning:
Do not drag the machine! It will damage the
machine’s structure.
Image 5
8 REQUIRED AREA FOR OPERATION
AND MAINTENANCE
Explanations in Article 5 and Article 6 should be
considered in determining the required area for
operation and maintenance.
9 WORKING ENVIRONMENT
TEMPERATURE
Machine should not be installed or used in
places, where the temperature may go below 0°C.