Engineering of insulation
9. Engineering of insulation
9.1 Insulation of refrigerant pipe
9.1.1 Operational procedure of refrigerant pipe insulation
Cut the suitable pipe → insulation (except joint section) → flare the pipe → piping layout and connection→
vacuum drying → insulate the joint parts
9.1.2 Purpose of refrigerant pipe insulation
During operation, temperature of gas pipe and liquid pipe shall be over-heating or over-cooling
extremely. Therefore, it is necessary to carry out insulation; otherwise it shall debase the performance
of unit and burn compressor.
Gas pipe temperature is very low during cooling. If insulation is not enough, it shall form dew and cause
leakage.
Temperature of gas pipe is very high (generally 50-100
℃
) during heating. Insulation work must be
carried out to prevent hurt by carelessness touching.
9.1.3 Insulation material selection for refrigerant pipe
The burning performance should over 120
℃
According to the local law to choose insulation materials
The thickness of insulation layer shall be above 10mm.If in hot or wet environment place, the layer of
insulation should be thicker accordingly.
9.1.4 Installation highlights of insulation construction
Gas pipe and liquid pipe shall be insulated separately, if the gas pipe and liquid pipe were insulated
together; it will decrease the performance of air conditioner.
Liquid pipe
Insulation meterial
Gas pipe
The insulation material at the joint pipe shall be 5~10cm longer than the gap of the insulation material.
The insulation material at the joint pipe shall be inserted into the gap of the insulation material.
The insulation material at the joint pipe shall be banded to the gap pipe and liquid pipe tightly.
The linking part should be use glue to paste together
Be sure not bind the insulation material over-tight, it may extrude out the air in the material to cause bad
insulation and cause easy aging of the material.
9.2 Insulation of drainage pipe
9.2.1 Operational procedure of refrigerant pipe insulation
Select the suitable pipe → insulation (except joint section) → piping layout and connection→ drainage test→
insulate the joint parts
9.2.2 Purpose of drainage pipe insulation
The temperature of condensate drainage water is very low. If insulation is not enough, it shall form dew and
cause leakage to damage the house decoration.
Installation
61
Summary of Contents for ICS0629C21
Page 1: ...SERVICE MANUAL IOS629C2V01 IOS736C2V01 IUS0736C21 ICS0629C21 ICS0736C21 AIR CONDITIONER i ...
Page 2: ......
Page 4: ......
Page 9: ...Part 2 Indoor Units Four way Cassette Type 6 Ceiling Floor Type 20 5 ...
Page 13: ......
Page 16: ...Service Space 3 Service Space 1000mm 1000mm 1000mm 1000mm 12 Four way Cassette Type ...
Page 17: ...Wiring Diagrams 4 Wiring Diagrams ICS0629C21 ICS0736C21 Four way Cassette Type 13 ...
Page 23: ...Field Wiring 11 Field Wiring ICS0629C21 ICS0736C21 Four way Cassette Type 19 ...
Page 27: ...Service Space 3 Service Space Ceiling Floor Type 23 ...
Page 28: ...Wiring Diagrams 4 Wiring Diagrams IUS0736C21 24 Ceiling Floor Type ...
Page 35: ...Field Wiring 11 Field Wiring IUS0736C21 Ceiling Floor Type 31 ...
Page 40: ...Wiring Diagrams 3 Wiring Diagrams IOS629C2V01 36 Outdoor Unit ...
Page 41: ...Wiring Diagrams IOS736C2V01 Outdoor Units 37 ...