AIR PUMP INSTALLATION
Before installation, choose a mounting location for the chemical pumps that is as close as possible to chemical
containers. Be sure to allow enough space between pumps for ease of installation and service. Follow the installation
steps below for each chemical pump that will be used.
(1) Attach air input fitting provided in accy kit to the air inlet port on the pump.
(2) Attach inlet and outlet barb fittings provided in the accy kit.
(3) Mount pumps as close as possible to chemical and no more than 6 ft above chemical container.
(4) Connect pickup line to input side of pump.
(5) Connect discharge line between output side of pump and point of injection. If using a flush manifold, connect the
discharge line to corresponding port on manifold.
(6) Route and connect air line for each pump to corresponding air solenoid control box.
(7) Insert pickup line into appropriate chemical container.
(8) Prime all chemical pumps. This can be done with manual prime buttons on the main control board or the control
panel of the ILCS EDGE system.
(9) Adjust the flow rate of each chemical pump to desired setting using the air pressure regulators inside the main
control box. Each regulator has a built in air gauge.