PRE-INSTALLATION 

Before the equipment is installed, you should survey the installation site thoroughly. Listed below are some of the 
factors to consider when picking your location. 

 

Work Area — the unit should be mounted in centralized area to work areas. 

 

Chemical location — unit should be mounted close to the chemical tanks. For bulk tank installations, pumps must 
be placed on, or near tanks. 

 

Mounting surface — ensure there is a sturdy wall (or panel) with enough space for all system components and 
routing of chemical tubes, air lines, and cables. 

 

Electrical — requires 115 VAC/60 Hz power source, 1 amp service for air pump only applications (20 amp 
service recommended if using peristaltic pumps). 

 

Air Service — required for operation of air pumps and anti-siphon valves (optional if manifold is used). Available 
air pressure should be 70 PSI and 12 SCFM. Check specification of air compressor on site for adequate air flow. 

 

Water Service — system requires ambient water service to flush manifold (if so equipped). Recommended 
minimum 25 PSI flow pressure. 

 

Familiarize yourself with all applicable safety, electrical, and plumbing codes. 

CONTROL BOX & POWER SUPPLY INSTALLATION 

(1)  Mount the joggle bracket to the wall at a height that all users can access and read the display screen. Use the 

hardware in the accy kit or other appropriate hardware for the mounting surface. 

(2)  Hang the control box unit on the joggle bracket. Secure the control box to the wall with provided hardware. 

(3)  Mount the power supply box in close proximity to the control box unit. 

(4)  Connect main power from a suitable breaker to the power input terminal block inside the power supply box, and 

per local wiring codes. 

(5)  Connect power from the power supply box to the appropriate terminals on the main control board inside the 

control box using the cable provided (see wiring diagram in this manual for details). 

(6)  Connect air line to input fitting on the air filter inside the control box. Hardware not provided. 

(7)  Connect water supply (if flush will be used). Hardware not provided. 

Summary of Contents for Knight ILCS EDGE

Page 1: ...0900885 Rev REL 02 06 Page 1 of 12 ILCS EDGE System Installation Manual...

Page 2: ...am 10 Label Change Procedure 11 Warranty Information 12 Knight Locations 12 CAUTION Wear protective clothing and eyewear when dispensing chemicals or other materials Observe safety handling instructio...

Page 3: ...0900885 Rev REL 02 06 Page 3 of 12 S...

Page 4: ...ce for installing system components A Power Supply Isolates high voltage system operating power from the control box The power supply box contains a transformer and electrical noise filter for added p...

Page 5: ...0900885 Rev REL 02 06 Page 5 of 12 SYSTEMDIAGRAM B A C D E...

Page 6: ...dequate air flow Water Service system requires ambient water service to flush manifold if so equipped Recommended minimum 25 PSI flow pressure Familiarize yourself with all applicable safety electrica...

Page 7: ...to chemical and no more than 6 ft above chemical container 4 Connect pickup line to input side of pump 5 Connect discharge line between output side of pump and point of injection If using a flush man...

Page 8: ...port of the manifold This will leave 7 ports remaining for chemical pumps 4 Plugs should be installed in any of the unused ports of the manifold 5 Mount manifold to wall using appropriate hardware 6...

Page 9: ...nt signal commons see details below Splitting Signal Commons Shut off all power sources before continuing If you have one signal common typical connect it to COM A only If you have two signal commons...

Page 10: ...Page 10 of 12 0900885 Rev REL 02 06 SYSTEMWIRINGDIAGRAM...

Page 11: ...ont panel with alcohol in preparation for adhering the new label 7 Carefully remove the backing paper from the new label Route the ribbon cable through the slot in the front panel and adhere the label...

Page 12: ...Return Authorization KRA number freight prepaid and found to be defective upon factory authorized inspection Bearings and pump seals or rubber and synthetic rubber parts such as O rings diaphragms sq...

Reviews: