2.4 Installation Procedure
1. Read this manual thoroughly before Installing, Operating, or Maintaining this lift.
2. Site Evaluation and Lift Location
A. Always use an architect
’s plan when provided. Before unpacking the lift entirely, determine if the
site is adequate for the lift model being installed see figures 1 & 2 for typical bay layout and ceiling
height requirements. It is recommended to have 144
” (12’) minimal celling height.
B. Snap chalk lines to identify the lift
’s centerline.
C. Snap a chalk line parallel to the lift
’s centerline,
spaced 9.00”
toward the rear of the bay. This line
represents the back edge of the column bases.
D. Snap chalk lines parallel to the lift
’s centerline
spaced 68-7/8”
to the left and 68-7/8” to the right
.
These lines represent the
APPROXIMATE
outside edges of the column bases.
DO NOT USE THESE LINES TO POSITION THE COLUMNS, FOLLOW THE INSTRUCTIONS IN
THIS MANUAL.
3. Unpack the Lift
A.
Remove the swing arms, bolt box, power unit box, and overhead beam.
B.
Save all packing hardware
, as these components
are necessary to complete
the installation.
C.
Remove the 1/2” bolts from the uprights
which hold the two columns together.
D.
Remove the upper column
.
Do not stand the columns up
now but lay the columns with their flat
backs on the floor.
4. Attach Cylinder Mounts
A. Connect cylinder mounts to top of each column
using 4ea 1/2” x 1-3/4” bolts, washers and nuts
provided as shown in figures 4a & 4b.
Fig. 4a