12
Mexico Super RS 3/60P - 3/100P -
Installation
INSTALLATION
6
PREPARING THE BOILER
Notes
.
z
Before placing the boiler in the selected position any
gas and water connections at the rear of the boiler
should be prepared, due to the possible lack of access.
z
If an optional Pump Kit is to be used then it must be
fitted at this stage. Refer to separate fitting instructions
included with the kit.
z
The pump may be fitted to the FLOW or the RETURN.
1.
Screw the distributor tube (supplied with a 1" BSP x
28mm copper adaptor) into the selected heating return
tapping, using an appropriate jointing material.
INST
ALLA
TION
Connections - as viewed at front
Thermostat Position
Back Section
Front Section
CH
DHW
Flow Return
Flow
Return
Top
LH
LH
RH
RH
LH
LH
RH
RH
LH
LH
RH
RH
LH
LH
RH
RH
LH
LH
RH
RH
7
PREPARING THE WALL
Boiler Size
Dim. A
Dim. B
RS 3/60P
696 (27
3/8
")
200(7
7/8
")
RS 3/75P
672 (26
1/2
")
248 (9
3/4
")
RS 3/100P
626 (24
5/8
")
340 (13
3/8
")
IMPORTANT.
It is
IMPERATIVE
that the index mark on the distributor tube
bush is in alignment with the mark on the section boss, as
shown in Frame 3.
DO NOT disturb it when connecting subsequent pipework.
Fully pumped systems using more than 1 pump, serving
separate zones, must have a common return connection
to the distributor tube.
2.
Select the desired pumped flow tapping.
3.
Screw the supplied boiler thermostat pocket into the
appropriate front section tapping, using an approved
jointing material. Refer to Tables 7 and 8.
4.
Connect pipe fittings to the rear tappings and plug any
unused tappings.
Note
.
If using iron elbows fit a short straight connector into
the boiler tapping first, to clear the casing.
Table 8 - Gravity Domestic Hot Water
and Pumped Central Heating
Connections - as viewed at front
Thermostat Position
Back Section
Front Section
Flow
Return
Top
LH
LH
LH
LH
RH
LH
RH
RH
RH
RH
LH
RH
Table 7 - Fully Pumped Systems
b.
The terminal MUST NOT
come into contact with a
combustible material such as
that used in non-standard
construction of timber frame
and plasterboard etc.
2.
Place the boiler in the selected
position.
Note.
If an extension duct D is to
be fitted, this must be done
BEFORE the boiler is placed in
position. Refer to Frame 10.
3.
Make good the brickwork around
the air duct.
1
. Cut the appropriate hole in the wall for insertion of the terminal
assembly.
Notes.
a.
Make good the hole on the INSIDE of the building to the
given dimensions BEFORE fitting the boiler, to facilitate
sealing between the terminal and the wall when the boiler is
in position.