5
VI. The Nuclear Phase Operation
(1) High-pressure nuclear
Will be hooked up to two live line, X, Y launcher, watch the receiving host measurements
(according to the national grid, nuclear grade A standard). More than 30 degrees are
heterogeneous, "heterogeneous" indicator, voice prompt "phase-out please note" at the
same time; Less than 30 degrees are in phase, "in phase" indicator, the voice prompt "in
phase" at the same time. Operation schematic diagram is as follows:
(2) Switchgear nuclear phase induction electric point
Wiring methods as follows in figure 4, as a result, check method and high-pressure
nuclear phase is the same