Acceptance Manual
Tecal RH2485 V2 Server
Part II Operation Guide
2
Test Description
None
T01-03 PSU
T01-0301 Verifying the PSU Installation and Power-on State
Objective
To verify the installation and power-on status of the power supply units (PSUs)
Test Networking
Diagram
None
Preset Conditions
The structure of the mainboard, hard disk backplane, I/O board, indicator board, VGA
board, and power board is proper.
Test Procedures
1.
Insert the two PSUs into the slots. If only one PSU is configured, install a filler
panel in the other slot.
2.
Connect the PSUs to the power input socket over power cables, and wait 10
seconds.
Expected Result
1.
The PSUs and filler panel are installed smoothly and properly.
2.
The PSUs fit the chassis properly.
3.
The PSUs are working properly and the indicators are steady green when the
server is being powered on.
4.
No abnormal noise is heard during the power-on operation.
Test Description
None
T01-0302 Verifying the Hot Swap Function
Objective
To verify that the PSUs are hot-swappable
Test Networking
Diagram
None
Preset Conditions
The structure of the mainboard, hard disk backplane, I/O board, indicator board, VGA
board, and power board is proper.
Test Procedures
1.
Insert one PSU into the slot.
2.
Connect the power cables and wait 10 seconds till the server is powered on.
3.
Insert the other PSU into the slot. Check that the power status indicator is
steady on.
4.
Remove the first PSU from the chassis.
5.
Insert the first PSU into the slot. Check that the power status indicator is steady
on.
6.
Remove the second PSU from the chassis.
Expected Result
The server is working properly during the test, and no power failure occurs.
Test Description
None