optic cables and use the other sling as a traction sling to secure the cables 4 m (13.12 ft)
away from the lifting sling, as shown in
.
Figure 6-7
Binding fiber optic cables
(1) Lifting sling
(2) Stretch sling
(3) Traction sling
NOTICE
Do not remove the stretch sling and protection pipe or bind fiber optic cables using one
sling, as shown in
Figure 6-8
Incorrect binding method
3.
Installation engineer B rotates the fiber spools at the speed of 5 m (16.4 ft) to 15 m (49.21
ft) per minute to coil the fiber optic cables.
RRU3942&RRU3642
Installation Guide
6 Hoisting an RRU and Related Cables onto a Tower
Issue 07 (2013-12-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
46