Installation Manual
iSiteC BTS3601C CDMA Base Station
Hardware Installation
2
Installing Cabinet Hardware
2-22
2)
Starting from the inside of the rack, install the two M4
%
45 screws at the upper part
of the rack, then check the correspondence between the two screws (at the lower
part) and the fastener set 2. If OK, tighen the screws; otherwise, adjust the position
of fastener set 2, as shown in Figure 2-20.
1) M4
%
45 screw
2) Rack
Figure 2-20
Fixing the rack
Caution:
Check the levelness of the rack after the installation and confirm the result not over 1° so as to ensure the
cooling of the MPAM. Otherwise, adjust it till it is OK.
2.3.5 Installing Modules
Modules of BTS3601C are generally installed by the sequence from right to left, i.e.
MPAM-MFEM-MTRM-MBPM-MAPM. During the installation, refer to their names on
the front of the modules and the corresponding names on the backplane, then insert
them into the corresponding slots.
Figure 2-21 shows the installation flow of modules.