Figure 4-7 Installing a ground cable
(1) Site ground bar
----End
4.3 Installing Components
4.3.1 Installing an SMU11B
Procedure
Step 1 Insert the SMU11B into the slot and slide it into the subrack along the guide rails.
Step 2 Push the SMU11B handle upwards until it is in place.
Figure 4-8 Installing an SMU11B
----End
4.3.2 Installing an SMU11C
Procedure
Step 1 Set the DIP switch based on the assigned address.
Step 2 Insert the SMU11C into the slot and slide it into the subrack along the guide rails.
Step 3 Push the SMU11C handle upwards until it is in place.
ETP4860-B1A2 Embedded Power
User Manual
4 Installation
Issue 04 (2021-01-05)
Copyright © Huawei Technologies Co., Ltd.