Installation
33
User Manual
Figure 30: Sliding the Blades in the Rails
Step 5.
Secure the system in the rack by tightening the 8 screws inserted in Step 3 and Step 4 with a
torque of 4.5±0.5 Nm.
2.5.4 Side by Side Mounting for SN2100M/SN2010M Rail Kit
The installation process is demonstrated on an SN2100M system, but applies to the
SN2010M series as well.
A designated rail kit for the SN2100M/SN2010M systems can be purchased sepa-
rately.
This section is relevant to short-depth systems that allow such form of installation
only.
At least two people are required to safely mount the system in the rack.