General Site Preparation Guidelines
Sample of an Installation Schedule
Chapter 2
32
Sample of an Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
•
60 days before installation
— Floor plan design completed and mailed to Hewlett-Packard (if required to be an HP task)
•
30 days before installation
— Primary power and air conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— A signed copy of the site inspection and delivery survey mailed to Hewlett-Packard
— Site inspection and predelivery coordination meeting arranged with a Hewlett-Packard
representative to review the inspection checklist and arrange an installation schedule.
•
7 days before installation
— Final check made with HP site preparation specialists to resolve any last minute problems
NOTE
Not all installations follow a schedule like the one noted above. Sometimes, an hp Integrity
rx5670 is purchased through another vendor which can preclude a rigid schedule. Other
conditions could also prevent following this schedule. For those situations, consider a milestone
schedule.
•
Site Preparation—schedule with the customer as soon as possible after the order is placed.
•
Site Verification—schedule with the customer a minimum of one to two days before the hp
Integrity rx5670 is scheduled to be installed.
Summary of Contents for Integrity rx5670
Page 4: ...Contents 4 Power Cable 43 Glossary 45 ...
Page 10: ...System Specifications Environmental Specifications Chapter 1 10 ...
Page 30: ...General Site Preparation Guidelines Space Requirements Chapter 2 30 Equipment cable routing ...
Page 42: ...Power Plug Configuration Male End of Power Cable Chapter 3 42 Figure 3 10 GB 1002 Plug ...
Page 44: ...Power Plug Configuration Power Cable Chapter 3 44 ...