General Site Preparation Guidelines
Facility Characteristics
Chapter 2
26
Facility Characteristics
This section contains information about facility characteristics that must be considered for the installation or
operation of an hp Integrity rx5670. Facility characteristics are:
•
Floor loading
•
Windows
•
Altitude effects
Floor Loading
The computer room floor must be able to support the total weight of the installed hp Integrity rx5670 as well
as the weight of the individual cabinets as they are moved into position.
Floor loading is usually not an issue in nonraised floor installations. The information presented in this section
is directed toward raised floor installations.
NOTE
An appropriate floor system consultant should verify any floor system under consideration for
an hp Integrity rx5670 installation.
Raised Floor Loading
Raised floor loading is a function of the manufacturer’s load specification and the positioning of the
equipment relative to the raised floor grid. While Hewlett-Packard cannot assume responsibility for
determining the suitability of a particular raised floor system, it does provide information and illustrations
for the customer or local agencies to determine installation requirements.
The following guidelines are recommended:
•
Because many raised floor systems do not have grid stringers between floor stands, the lateral support for
the floor stands depends on adjacent panels being in place. To avoid compromising this type of floor
system while gaining under floor access, remove only one floor panel at a time.
•
Larger floor grids (bigger panels) are generally rated for lighter loads.
CAUTION
Do not position or install any equipment cabinets on the raised floor system until you have
carefully examined it to verify that it is adequate to support the appropriate installation.
Summary of Contents for Integrity rx5670
Page 4: ...Contents 4 Power Cable 43 Glossary 45 ...
Page 10: ...System Specifications Environmental Specifications Chapter 1 10 ...
Page 30: ...General Site Preparation Guidelines Space Requirements Chapter 2 30 Equipment cable routing ...
Page 42: ...Power Plug Configuration Male End of Power Cable Chapter 3 42 Figure 3 10 GB 1002 Plug ...
Page 44: ...Power Plug Configuration Power Cable Chapter 3 44 ...