142
RP-2002 Series Manual —
P/N 53039:E6 1/26/2017
NFPA Standard-Specific Requirements
Notes:
1.
Reference the 411UD Manual for additional information
2.
All connections between the RP-2002 and the 411UD must be in conduit, less than 20 ft. (610
cm) in length in the same room.
3.
Any zone of the 411UD can be wired to function as alarm, trouble or supervisory; the 411UD
must be programmed accordingly. In this example, Channel/Zone 1 is wired to the control
panel’s alarm relay, Channel 2/Zone 2 is wired to the control panel’s trouble relay and Channel
3/Zone 3 is wired to the control panel’s supervisory relay.
4.
Nonresettable 24 VDC power is supplied to the 411UD via TB9 terminals configured for
nonresettable power on the FACP. Jumper J4 on the 411UD must be removed for 24 VDC
power.
5.
End-of-Line resistors must terminate all 411UD circuits, including unused circuits.
6.
Program the 411UD for slave operation.
7.
The RP-2002 must be programmed for AC Loss Reporting Delay This prevents the immediate
transmission of a trouble on the loss of AC power.
8.
A (-)VDC from the 411UD Trouble Contacts will activate the Trouble Input J6 on the FACP
when the 411UD goes into DACT Trouble (the 411UD Trouble Contact is programmed as
DACT Trouble).
411UD
FACP
Alarm
TB2-1
TB8-1
TB2-2
TB8-3
Trouble
TB2-3
TB8-4
TB2-4
TB8-6
Supervisory
TB2-5
TB8-7
TB2-6
TB8-9
Table C.1 411-UD Connections to FACP
Summary of Contents for NOTIFIER RP-2002C
Page 158: ...Cut along dotted line ...