3Dimensions System User Guide
Chapter 4: Startup, Functional Tests, and Shutdown
MAN-05085-002 Revision 002
Page 29
DRAFT
Preview Copy-Generated May 30, 2018
4:
Startup, Functional Tests, and Shutdown
4.1
How to Start the System
Note
If the system remains on overnight, restart the system daily to guarantee best
performance.
1.
Make sure that there are no obstructions to C-arm movement or to the view of the
Operator.
2.
Make sure that all three Emergency Off switches are in the reset position (unpushed).
Figure 14: Turn to Reset the
Emergency Off Switches
3.
Make sure that the Gantry circuit breaker is in the ON position.
4.
If the UPS was turned OFF, press the UPS power button to apply power to the UPS
(see the following figure).
Figure 15: Universal Acquisition
Workstation Power Buttons
Figure Legend
1. Acquisition Workstation Power Switch
2. Computer Power On/Reset Button
3. UPS Power Button
5.
Turn ON the Acquisition Workstation power switch (see the previous figure).
Chapter 4