Chapter
3:
Installing the SVP3
The physical SVP3 is installed in the rack above the controller and drive trays using a rail
kit, brackets, and a bezel. The brackets are installed on the vertical struts of the rack, and
then the bezel is attached/wedged around these brackets.
Caution: The manual voltage selector switch must set to the correct voltage
before installing the rail kit to the SVP3.
SVP3 mounting considerations
Mounting the physical SVP3 appropriately in the rack is important to ensure optimum
performance.
When mounting the SVP3, consider the following:
■
Installing the SVP3 in the top bay of the rack or as close to the top bay as possible.
■
Leaving approximately 25 inches in front of the rack to enable you to open the front
bezel.
■
Leaving approximately 30 inches of clearance in the back of the rack to allow for
sufficient airflow and ease in servicing.
Setting the voltage selector switch
To prevent damage to the SVP3 power supply, you must set the voltage selector switch to
the correct voltage (115V or 230V) before you install the rack kit on the SVP3.
Before you begin
■
Verify the onsite supply voltage that will be connected to the storage system and
SVP3.
Procedure
1. Remove the yellow voltage confirmation label that covers the power cord inlet on
the SVP3.
Chapter 3: Installing the SVP3
Service Processor 3 (SVP3) Technical Reference
15