Hilti HIT-RE 100 mortar w/     

rebar (as post-installed conn.)

 

 
 

04 / 2016 

                                            9 

 

 

Setting the element 

 

Before use verify that the element is dry and free of oil and other 
contaminants. 

 

 

 

 

For easy installation insert the rebar slowly twisted into the drill hole 
until the embedment mark is at the concrete surface level. 

 

 

 

 

For overhead application: 
 
During insertion of the rebar, mortar might flow out of the borehole. 
For collection of the flowing mortar, HIT-OHC may be used. 
 
Support the rebar and secure it from falling till mortar started to 
harden, e.g. using wedges HIT-OHW. 
 
For overhead installation use piston plugs and fix embedded parts 
with e.g. wedges. 

 

 

 

 

After installing the rebar the annular gap must be completely filled 
with mortar. 

Proper installation: 

 

desired anchoring embedment l

v

 is reached: embedment 

mark at concrete surface.  

 

excess mortar flows out of the drill hole after the rebar has 
been fully inserted until the embedment mark.  

 

 

 

Observe the working time t

work

, which varies according to temperature 

of base material. Minor adjustments to the rebar position may be 
performed during the working time.  

 

 

 

 

 

Full load may be applied only after the curing time t

cure

 has elapsed.  

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Summary of Contents for HIT-RE 100

Page 1: ...suitable for embedment length till 3200 mm Statik mixer Rebar Base material Load conditions Concrete Dry concrete Wet concrete Static quasi static Installation conditions Other informations Hammer dri...

Page 2: ...6 Setting details For detailed information on installation see instruction for use given with the package of the product Curing time for general conditions 1 Data according ETA 15 0883 issue xxx Tempe...

Page 3: ...drill hole the drill hole shall be filled with mortar Drill the hole to the required embedment depth using a hammer drill with carbid drill bit set in rotation hammer mode a compressed air drill or a...

Page 4: ...essed air cleaning CAC For all drill hole diameters d0 and all drill hole depths h0 20 d Blow 2 times from the back of the hole if needed with nozzle extension over the whole length with oil free comp...

Page 5: ...DRS is recommended In addition for wet diamond corind DD For all drill hole diameters d0 and all drill hole depths h0 Flush 2 times by inserting a water hose water line pressure to the back of the ho...

Page 6: ...d above For each new foil pack a new mixing nozzle must be used Discard quantities are 3 strokes for 330 ml foil pack 4 strokes for 500 ml foil pack 65 ml for 1400 ml foil pack Inject adhesive Inject...

Page 7: ...ction Mark the required mortar level m and embedment depth v with tape or marker on the injection extension estimation lm 1 3 lv precise formula for optimum mortar volume lm lv 1 2 2 d0 2 0 2 For over...

Page 8: ...it from falling till mortar started to harden e g using wedges HIT OHW For overhead installation use piston plugs and fix embedded parts with e g wedges After installing the rebar the annular gap mus...

Page 9: ...Diamond coring Dry PCC Wet DD 8 12 10 a 12 10 a 10 14 12 a 14 12 a 12 16 14 a 17 16 14 a 14 18 17 18 16 20 20 20 18 22 22 22 20 25 24 b 26 25 22 28 28 28 24 32 32 35 32 25 32 30 b 32 30 b 35 32 26 35...

Page 10: ...ions multiply the values by 0 7 Bond strength in N mm according to ETA 15 0883 for good bond conditions diamond coring wet Rebar mm Concrete class C12 15 C16 20 C20 25 C25 30 C30 37 C35 45 C40 50 C45...

Page 11: ...22 C20 25 2 3 165 3 330 312 1040 728 22 C50 60 4 3 165 3 330 220 556 389 24 C20 25 2 3 196 6 360 340 1134 794 24 C50 60 4 3 196 6 360 240 607 425 25 C20 25 2 3 213 4 375 354 1181 827 25 C50 60 4 3 21...