Installing the
Installing the HPE
HPE 800 W Flex Slot -48 VDC hot-plug power supply
800 W Flex Slot -48 VDC hot-plug power supply
The DC power supply option kits do not ship with a Power Supply DC cable Kit and may not include a Power Supply Cable Lug kit. The
optional DC Cable kit or the optional DC Cable Lug Kit may be purchased directly from Hewlett Packard Enterprise or an authorized
HPE reseller. For additional information, refer to the power supply QuickSpecs at https://www.hpe.com/info/fsps-qs
https://www.hpe.com/info/fsps-qs.
WARNING:
WARNING:
To reduce the risk of electric shock, fire, and damage to the equipment, you must install this
product in accordance with the following guidelines:
The HPE 800 W Flex Slot -48 VDC hot-plug power supply is intended only for installation in
Hewlett Packard Enterprise servers located in a restricted access location.
The HPE 800 W Flex Slot -48 VDC hot-plug power supply is not intended for direct
connection to the DC supply branch circuit. Only connect this power supply to a power
distribution unit (PDU) that provides an independent overcurrent-protected output for each
DC power supply. Each output overcurrent-protected device in the PDU must be suitable for
interrupting fault current available from the DC power source and must be rated no more
than 30 A.
The PDU output must have a shut-off switch or a circuit breaker to disconnect power for
each power supply. To completely remove power from the power supply, disconnect power
at the PDU. Disconnect the power for each power supply, if there are multiple power
supplies.
In accordance with applicable national requirements for Information Technology Equipment
and Telecommunications Equipment, this power supply only connects to DC power sources
that are classified as SELV or TNV. Generally, these requirements are based on the
International Standard for Information Technology Equipment, IEC 60950-1/IEC 62368-1. In
accordance with local and regional electric codes and regulations, the DC source must have
one pole (Neutral/Return) reliably connected to earth ground.
You must connect the power supply ground screw located on the front of the power supply
to a suitable ground (earth) terminal. In accordance with local and regional electric codes
and regulations, this terminal must be connected to a suitable building ground (earth)
terminal. Do not rely on the rack or cabinet chassis to provide adequate ground (earth)
continuity.
Prerequisites
Prerequisites
Before you install this option, make sure that you have the following items available:
No. 1 Phillips screwdriver
Optional Q0H80A HPE 800W DC Power Cable Kit can be purchased from an HPE authorized reseller.
If you are not using an input power cord option, the power supply cabling must be made in consultation with a licensed electrician
and be compliant with local code.
If you are replacing the factory installed ground lug, use the KST RNB5-5 crimp terminal ring or equivalent. Use an M5-0.80 x 8
screw to attach the ground lug to the power supply.
Procedure
Procedure
1. Remove the power supply blank.
Installing the HPE 800 W Flex Slot -48 VDC hot-plug power supply
78
Summary of Contents for HPE ProLiant DL345 Gen10 Plus
Page 28: ...HPE Basic Drive LED definitions 28...
Page 33: ...Fan bay numbering The arrow points to the front of the server Fan bay numbering 33...
Page 46: ...Removing a riser cage 46...
Page 54: ...Operational requirements Operational requirements 54...
Page 68: ...Installing the bezel and bezel lock Installing the bezel and bezel lock 68...
Page 91: ...Connecting a DC power cable to a DC power source 91...
Page 115: ...Riser and riser cage options Riser and riser cage options 115...
Page 120: ...Expansion slots Expansion slots 120...
Page 129: ...The installation is complete Installing an accelerator or GPU 129...
Page 144: ...Installing the Trusted Platform Module board Installing the Trusted Platform Module board 144...
Page 156: ...Storage cabling Storage cabling 156...
Page 157: ...Drive power cabling Drive power cabling 157...
Page 160: ...2 SFF drive power cabling 2 SFF drive power cabling 160...
Page 161: ...Storage controller cabling Storage controller cabling 161...
Page 191: ...Energy pack cabling Energy pack cabling 191...
Page 193: ...Storage controller backup power cabling 193...
Page 194: ...M 2 SATA SSD cabling M 2 SATA SSD cabling 194...
Page 196: ...Fan cabling Fan cabling 196...
Page 197: ...OCP bandwidth upgrade cabling OCP bandwidth upgrade cabling 197...
Page 198: ...Serial port cabling Serial port cabling 198...
Page 199: ...Chassis intrusion detection switch cabling Chassis intrusion detection switch cabling 199...
Page 200: ...Front I O cabling Front I O cabling 200...
Page 201: ...Software and configuration utilities Software and configuration utilities 201...
Page 229: ...Keeping the system current Keeping the system current 229...
Page 242: ...Troubleshooting Troubleshooting 242...
Page 245: ...System battery replacement System battery replacement 245...
Page 249: ...Safety warranty and regulatory information Safety warranty and regulatory information 249...
Page 253: ...Ukraine RoHS material content declaration Ukraine RoHS material content declaration 253...
Page 255: ...Specifications Specifications 255...
Page 268: ...Support and other resources Support and other resources 268...