21D-265C
61
Applied operation
7-3. Working setting B
,
C - Operation when
“No” for working hour setting is set(With Tact
reserve function)
This article describes about the Working setting
“
B
”
/
“
C
”
.
When the Working setting (M=?)is displayed as
“
B
”
or
“
C
”
in the Operating status
screen, the Function setting is carried out as described in the following table.
Working
setting
With/Without Tact reserve
function [5]
With/Without working hour
[6]
Tact
reservation
Cumulative
display
For use of working hours
“
B
”
Yes
No
No
“
C
”
Yes
Yes
No
The Working setting
“
B
”
/
“
C
”
is the operation including of Tact reserve function in
addition to the Working setting
“
A
”
, which allows the planned quantity to be calculated
without setting the working hour while the signal being outputted from outside is
regarded as
“within working hour”.
To reserve the tact according to this operation, register
“Tact” and “Target production
quantity
” beforehand.
(For the Working setting
“
B
”
/
“
C
”
, the setup time is not registered.)
<Tact reserving procedure>
Set in the same way as for
“7-1”. However, the setup time is not registered.
<To switch the tact reserve No.>
Set in the same way as for
“7-1”.
<Clear processing>
[Clear] terminal
Plan/Actual is cleared and calculation is started from the present time
according to the tact of the current reserve No.
[CLR] key
Plan/Actual is cleared and calculation is started from the present time
according to the tact of the current reserve No.
<Tact switching timing>
The tact is switched into the next tact at the timing when the target production quantity is
consistent with the production actual.
Processing is carried out within working hour for the range between the reserve No.
registered as
“1” and the reserve No. ahead of either [0] in tact or [0] in production actual.
If operating terminal input is ON, processing continues after retuning to reserve No. 1.