21D-265C
55
Applied operation
<Message in registering>
When the amount of reserved tact (man-hours), labor hours calculated based on the
production reserved quantity and setup time in total exceeds the working hour for one day,
the overrun time is displayed.
When the amount of reserved tact (man-hours), labor hours calculated based on the
production reserved quantity and setup time in total does not exceed the working hour for
one day, the surplus time is displayed.
*Since the message only indicates the time difference between the working hour and the
reserved time, it does not affect on the processing. The displayed time is for your
reference in reserving/registering.
*When
“No” for use of working hour is set in the Function settings, the above overrun and
surplus time are not displayed.
<To change the tact reserve No.>
In normal processing, data is switched in the order registered in Tact reservation; however,
if processing should be started with the tact reserved work other than the work being
currently processed, this setting should be carried out.
The tact reserve No. switching method includes the following two ways:
1.Input the external signal to switch the current reserve No. into the next reserve No.
Each time when signal is turned on from the external input terminal
“
Tact switch
”
,
the Tact reserve No. is switched into the next reserve No.
2.Control the key to specify the reserve no and switch it.
To switch the reserve No through the control of key:
①
Press [F1] key.
Working
hour
(
)
in
over
It is displayed for about 4sec in registering.
Working
hour
(
)
in
surplus
It is displayed for about 4sec in registering.
{F1}T.Rsv
1:Rsv
2:Rsv
No.
[Tact reserve menu screen]