Fill Boiler With Water And Purge Air
NOTICE
To maintain boiler efficiency and prevent boiling
inside the heat exchanger, flush entire heating
system until clean.
•
Flush heating system, including all heating zones.
•
Fill boiler with potable water.
•
Fill boiler and system piping with water (or
antifreeze-water solution, if used). See antifreeze
information page 13. Purge air from boiler using
safety relief valve. Purge air from system piping.
•
Inspect system piping and boiler connections. Repair
any leaks immediately.
•
Activate all heating zones and calls for heat,
including CH calls and DHW calls (if available).
•
Close manual gas shut off valve. Let system run for
30 minutes. When boiler goes into lockout, reset
boiler by pressing "Reset" button until boiler resets.
•
Do not open gas shutoff valve until all air is purged
from system.
9.2
Fill Condensate Trap with Water
•
Remove spring tension clip from clear hose attached
to barbed fitting at bottom of boiler chassis.
See
figure 9-1.
•
Disconnect hose from barbed fitting.
•
Remove barbed fitting from boiler.
•
Attach supplied condensate trap to barbed fitting
using pipe tape.
•
Fill trap through fitting with approximately 2 cup
(473 ml) water.
•
Place barbed fitting back through bottom of chassis.
•
Reassemble clear tube to barbed fitting.
•
Secure tube to barbed fittting with spring tension clip.
See figure 9-1.
FIGURE 9-1 Condensate Drain Assembly
NOTICE
IMPORTANT: Condensate trap must be manually
filled with water at initial start up.
9 - START UP PROCEDURE
Condensate
Collector
Remove Spring
Tension Clip
Remove Hose
Barb
Attach Supplied
Condensate Trap
to Hose Barb
Secure Hose onto
Hose Barb with
Spring Tension
Clip
Summary of Contents for VX-050
Page 49: ...49 13 TROUBLE SHOOTING...
Page 51: ...51 13 TROUBLE SHOOTING...
Page 63: ...63 14 1 Connection Diagram 050 075 100 MBH 14 WIRING DIAGRAM...
Page 64: ...64 14 2 Schematic Diagram of Ladder Form 050 075 100 MBH 14 WIRING DIAGRAM...
Page 65: ...65 14 3 Connection Diagram 150 200 MBH 14 WIRING DIAGRAM...
Page 66: ...66 14 4 Schematic Diagram of Ladder Form 150 200 MBH 14 WIRING DIAGRAM...
Page 83: ...83 PRIMARY LOOP EQUIVALENT LENGTH CALCULATION PUMP SELECTION 50 75 100 MBH...
Page 84: ...84 PRIMARY LOOP EQUIVALENT LENGTH CALCULATION PUMP SELECTION 50 75 100 MBH...
Page 85: ...85 PRIMARY LOOP EQUIVALENT LENGTH CALCULATION PUMP SELECTION 150 200 MBH...
Page 86: ...86 PRIMARY LOOP EQUIVALENT LENGTH CALCULATION PUMP SELECTION 150 200 MBH...
Page 87: ...87 NOTES...
Page 88: ...DUNKIRK BOILERS 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com...