41
M
AINTENANCE
AND
S
ERVICING
Warning
Shock Hazard: Unplug power cord
before removing main power switch.
Figure 24: Power Switch Removal
Timer
The timer is part of the Display/Control Board. It indicates
the time only. It cannot interfere with the sterilization cycle.
When chamber pressure increases to about 20 psig (138
kPa), Pressure Switch closes. This enables the timer to
count down. Valve Shaft Switch must also be closed by
setting the control knob to PRESSURIZE.
Timer Check
If the timer does not function correctly, test Display/Control
Board.
•
Be sure the jumpers on the board are correct.
•
Replace Display/Control Board if required.
Power Switch
1.
Unplug the unit from the power source.
2.
Remove the top cover.
3.
Unplug connectors from switch terminals.
4.
Compress and hold spring clips at both sides of
switch (see Figure 24).
5.
Remove the switch from outside.
6.
Install replacement switch in reverse order. See
the Wiring Diagrams.
7.
If resistance values differ, the heater must be
replaced.
Summary of Contents for Chemiclave EC5500
Page 15: ...15 Figure 4 Metering Valve Function PRINCIPLES OF OPERATION ...
Page 16: ...16 Figure 7 Pressurization PRINCIPLES OF OPERATION Figure 6 Ready Load Figure 5 Warm Up ...
Page 17: ...17 Figure 8 EC5500 EC6000 Operation PRINCIPLES OF OPERATION ...
Page 18: ...18 Figure 11 End Unload Figure 10 Purge Figure 9 Exposure PRINCIPLES OF OPERATION ...
Page 20: ...20 Figure 13 Piping Schematic PRINCIPLES OF OPERATION ...
Page 21: ...21 Figure 14 Cycle Phase Diagram PRINCIPLES OF OPERATION ...
Page 22: ...22 Door Gasket Figure 15 Exploded View Top Cover and Door PRINCIPLES OF OPERATION ...
Page 32: ...32 MAINTENANCE AND SERVICING Figure 17 Metering Valve need new drawing ...
Page 39: ...39 MAINTENANCE AND SERVICING Figure 22 Power Supply Printed Circuit Board ...
Page 56: ...56 ...