background image

Carbon Film  
Installation Instructions 

Page 7 

 

Sensor Tip

50mm Gap

Depron

Cold Tails

Cold Tai

ls

Step 11

 

Fig. 12 

Position the floor sensor. 

If installing 

Heat-Pak® over the carbon system, refer to separate instructions regarding the floor 

sensor.  
For standard installation, the tip of the sensor sh

ould be approximately 300-500mm from the edge of the room with the tail 

of the probe running back to the thermostat via the 50mm cold tail gap. Fig. 12.  Form a channel in the foam underlay, in 
between two of the elements running into the cold tail gap.  Press the sensor into the channel and tape in place with self 
adhesive cloth tape. 
The sensor wire can be shortened or if required lengthened up to 50m with a minimum 0.75mm² 2-core flex cable. This 
connection should be located above floor level ideally within the cold tail junction box. 
It is advisable to mark on the installed location of the sensor tip, on the floor plan for future reference. 
Test the resistance of the floor probe.  Refer to the label on the floor probe wrapper for desired resistance readings.  Make 
a note of the reading.

 

When you are satisfied with the layout, cover the heating elements with the plastic sheet/moisture barrier provided

.  The 

grade of PE-Sheet supplied will depend upon what is being installed over the system. If a wood floor, engineered wood or 
laminate floor is being laid, a 100micron sheet (clear) will be provided. When fitting Heat-Pak® over a carbon heating sys-
tem a 200micron sheet (coloured blue) has to be used. The joints of the sheeting have to overlap by at least 20 cm. These 
overlaps have to be sealed over their total length with a self-adhesive PVC cloth tape (Duct Tape) 

Step 12

 

The floor finish can now be laid directly over the moisture barrier in accordance with the flooring manufacturers instruc-
tions.  

Under no circumstances 

should a separate underlay be installed at any point between the heating element and 

the floor finish.  Ensure that the floor finish has been acclimatised prior to installation to avoid excessive shrinkage when 
heated.  Refer to the notes on page 2 of this manual. 
During the process of laying the floor, care should be taken not to damage any of the heating elements or cold tails.  A 
spare sheet of foam underlay or a board, can be used to kneel on to help spread weight.

 

Step 13

 

Once the floor finish has been laid, perform resistance tests on the floor probe and across the feed cable that connects the 
thermostat to the junction box, to ensure that no elements have been damaged during the flooring installation.  The desired 
resistance reading for the heating system is at the bottom of the room test data sheet and should be within the tolerance of 

+

10 –5%.  Record the final readings on the guarantee certificate.  

Once this test has been completed, final connections to the thermostat can be made.  See Separate installation instruc-
tions for the thermostat.

 

Step 14

 

Summary of Contents for Carbon Film

Page 1: ...Page 3 Pre Installation Electrical Provision Page 4 Insulation Underlay Installation Page 5 Carbon Film Installation Under Wood Laminate Flooring Page 8 Notes Trouble shooting Carbon Film Installation...

Page 2: ...ue to their moisture content solid and kiln dried wood floor coverings should be laid but not fixed to allow acclimatisa tion with the heating system energised before final fixing Allowances should be...

Page 3: ...e heating is installed Make the electrical provision as per the diagram Fig 3 The circuit must incorporate a 30mA RCD protection For installations below 13Amp A fused spur or combined spur RCD is reco...

Page 4: ...anley knife or similar Step 2 Leave a gap of approximately 50mm at one edge of the room along where the cold cables are to be run so as to allow them to sit flush under the floor covering when it is l...

Page 5: ...d a coloured outer and a clear inner Carbon Film Installation Under Wood Laminate Flooring Only LIGHT FOOTWARE should be worn Avoid foot traffic on the heating elements and cold tail joints Un pack th...

Page 6: ...Step 7 Step 8 Fig 9 Step 9 Once the cold tails are in position a resistance test needs to be per formed on each individual element for a second time The desired resistance readings for each element ar...

Page 7: ...s being laid a 100micron sheet clear will be provided When fitting Heat Pak over a carbon heating sys tem a 200micron sheet coloured blue has to be used The joints of the sheeting have to overlap by a...

Page 8: ...ectrical contractor in respect of the individual heating circuit ratings relative to the thermostat rating circuit breakers interconnecting cable sizing and switched contactors where the load of the h...