43
Install a
13-7/8" x 48"
roof panel flush to the
installed panel and flush at peak
(Fig. B)
.
Secure panel with (2) 2" nails in the corners.
Move the gable until it is at 1/2"
(Fig. C)
from the
13-7/8" x 48"
roof panel.
Finish securing panel with (2) 2" nails in
the corners.
3
4
5
PARTS REQUIRED:
ROOF PANELS
x12
2" (5,1 cm)
NOTE:
Measurements are to outside of rafter.
Fig. D
2" (5,1 cm)
Nails
Maintain spacing between the center of the rafters
at the lower edge of the panels
(Fig. D)
.
Secure panels with (1) 2" nail into each rafter.
Move to the top of the panel and keep spacing
between the center of the rafters.
Secure panels with (1) 2" nail into each rafter.
Flush at
peak
Fig. B
24"
(61 cm)
24"
(61 cm)
24"
(61 cm)
24"
(61 cm)
24-3/8"
(61,9 cm)
24-3/8"
(61,9 cm)
Move
Gable
Flush
13-7/8"
x 48
"
1/2"
(1,2 cm)
Gable
End Rafter
Fig. C
Two Nails
13-7/8 x 48"
(35,2 x 121,9 cm)
x1