Installing Lights
2
3
4
1
5
6
Figure 12. Feeding the Electrical Cable
1. Feed end of cable into top of basket support pipe
2. Pull cable through basket support pipe
3. Pull cable through top half of pole
4. Pull cable through eyebolt
5. Pull cable down through bottom half of pole
6. Pull cable out access hole
HBA163
Installing the Internal Lighting Kit
After the basket has been attached to the pole, install the internal lighting kit.
This is done by performing the following steps.
1.
Remove the internal lighting kit components from the shipping pallet.
2.
Remove the two U-bolts from the lightbar, see Figure 13.
3. NOTE:
Place the lightbar across the center of the large end of the
basket, see Figure 13. The floodlights must point into the basket.
Position the bar horizontally, (parallel to the ground).
4.
Place the two U-bolts around the basket frame and back through the holes
in the lightbar, see Figure 13.
5.
Tighten the U-bolts to the basket frame.
6.
Place anti-locking compound on the basket support pole threads.
L-807 and L-806 Wind Cone Installation and Maintenance Manual
27