FoamLogix, Model 2.1A and 1.7AHP Class
“A”
Electronic Foam Proportioning Systems
69
SECTION 5 MAINTENANCE
MAINTENANCE PROCEDURES
1. After each use
Inspect wiring, hoses, flow sensors and
connections for tightness, corrosion, leaks and.
or damage. Refer to Figure 3 on page 21.
Flush foam pump if a non-approved foam
concentrate is used. Also see appendix A,
“Hale
Foam concentrate
Compatibility” beginning on
page 87 for recommended foam concentrates
.
2.
Monthly
Remove and clean the foam strainer screen.
Flush as required.
3.
Monthly
Verify water flow calibration.
4.
Annually
Verify foam feedback calibration.
5.
Every two (2) months
If an approved foam concentrate has been left in
the system, operate foam system to remove the
foam concentrate and prevent jelling.
FREEZE PROTECTION
Cold weather transport and cold weather storage of
FoamLogix systems:
• When transporting the completed fire
apparatus from the OEM to the dealer, and
the dealer to the end-user, or, when the end-
user decides to store the finished apparatus
in an unheated area subject to below freezing
temperatures, a FoamLogix winterization
process must be used.
• Any water and/or foam concentrate that
is in the foam concentrate reservoir, foam
concentrate pump, and associated foam
system piping/tubing will freeze and then
break system components when the system
is subjected to subfreezing temperatures
commonly found in over-the-road driving
during fire truck delivery and transport. The
following precautions must also be taken
by OEMs, end-users, re-sellers, fire truck
dealers, transport agencies, etc., that will be
transporting and/or storing the apparatus in
below freezing temperatures:
o Drain the foam concentrate storage
reservoir in accordance with safe foam
concentrate handling practices as outlined
by the foam concentrate manufacturer. If
the foam reservoir is filled with only water,
completely drain the storage compartment
of water. After empty, close all drain valves.
o Pour in five gallons (18.93L) of an
appropriate antifreeze solution in the foam
concentrate reservoir. Consider using an
environmentally friendly biodegradable
formulation.
o Follow the Installation and operation manual
procedure to
“prime” the foam pump.
o With the apparatus fire pump in gear, a
water supply established, and a discharge
hose and nozzle attached to the discharge
side of the fire pump, discharge over
100-gpm (380 LPM)from a foam capable
discharge.
o Turn the FoamLogix system
“on.” Depress
the
“up” arrow and raise the proportioning
rate to 3.0%.
o Continue to discharge water out of the
discharge hose for one-minute.
o Shut the FoamLogix system
“Off.”
o Shut off the discharge valve and shut the
fire pump down. Remove the water supply
connection to the fire pump.
Summary of Contents for FoamLogix 1.7AHP
Page 4: ...FoamLogix Model 2 1A and 1 7AHP Class A Electronic Foam Proportioning Systems 4 NOTES...
Page 10: ...FoamLogix Model 2 1A and 1 7AHP Class A Electronic Foam Proportioning Systems 10...
Page 14: ...FoamLogix Model 2 1A and 1 7AHP Class A Electronic Foam Proportioning Systems 14 NOTES...
Page 28: ...FoamLogix Model 2 1A and 1 7AHP Class A Electronic Foam Proportioning Systems 28 NOTES...
Page 52: ...FoamLogix Model 2 1A and 1 7AHP Class A Electronic Foam Proportioning Systems 52 NOTES...