7. Install the double platform splice (20) with intermediate support angles (5) to the platform floor (7) in
each section and inside kick plate (23) using eight truss head bolts (1), eight flange bolts (2) and six-
teen flange nuts (3) to secure the two platform sections.
Figure 5-15
Installing the double platform splice for second section
1
5/16 x 3/4 in. truss head bolt (S-10267)
7
Platform floor pan (WBS-0011)
2
5/16 x 3/4 in. flange bolt (S-6606)
20
Double platform splice,
For 24 ft and 30 ft bins (WBS-0084)
For 36 ft ft bins (WBS-0045)
3
5/16 in. flange nut (S-3611)
23
Inside kick plate (WBS-0014)
5
Intermediate support angle (WBS-0017)
60
PNEG-2077
TopDry – Platforms and Bin Stairs