![GSi PNEG-1894 Installation Manual Download Page 18](http://html1.mh-extra.com/html/gsi/pneg-1894/pneg-1894_installation-manual_2274989018.webp)
4. Installation
18
PNEG-1894
TopDry Chute Controller
Installing the Housing Assembly
1. Lift the housing assembly onto the lower mounting gussets (A), aligning holes in the bottom
of the chute position controller enclosure with the holes in the lower mounting gussets.
2. Remove cover to attach chute position controller enclosure to gussets with six (6) flange bolts (B)
and flange nuts (C).
3. Field drill all four (4) holes in the bin sidewalls through the four (4) holes in the sidewall mounting
brackets (D), making sure that the holes are drilled on the peaks of the corrugation ridges. Use bolts
to attach housing to bin.
Figure 4G
Ref #
Part #
Description
A
TD-101326
Lower Mounting Gussets
B
S-6606
Flange Bolt 5/16"-18 x 3/4" ZN Grade 5
C
S-3611
Flange Nut 5/16"-18 YDP Grade 2
D
TD-101331
Sidewall Mounting Bracket
Chute position controller enclosure weighs approximately 275 lbs. pounds. Failure
to use proper equipment and personnel when lifting could cause bodily injury or
damage to equipment.
WARNING
Summary of Contents for PNEG-1894
Page 1: ...PNEG 1894 TopDry Chute Controller Installation Manual PNEG 1894 Version 5 1 Date 09 27 20...
Page 12: ...12 PNEG 1894 TopDry Chute Controller 3 Controller Layout Figure 3A Chute Pulley Cable Location...
Page 14: ...4 Installation 14 PNEG 1894 TopDry Chute Controller Figure 4C...
Page 23: ...PNEG 1894 TopDry Chute Controller 23 5 Wiring and Schematic Diagrams Actuator Wiring Schematic...