GREER Company MicroGuard RCI 510 Operation Download Page 12

MicroGuard 510 Upgrade 

Erecting the Jib 

The erected jib button will select the erected jib when 
a stowed jib is present. The available erected jib 
options will be displayed in the information window.

Note: If the erected jib button is pressed when the 
system does not have a stowed jib selected, the 
message “There Is No Stowed Jib To Erect” will 
appear in the information window.

Auxiliary head

An auxiliary head fitted on a crane must be included 
in the crane setup. If the auxiliary head push button 
is pressed on a crane that does not have an auxiliary 
head, the message, “No Other Auxiliary Head Options” 
will appear in the information screen.

Selecting the Winch

For cranes with two winches, always select the winch 
to be used for the lift before selecting the point-of-lift 
and parts-of-line. The system stores point-of-lift and 
parts-of-line selections for each winch. If no other 
winch is available, the message “No Other Winch 
Options” will appear. 

Selecting the Point of lift 

Before choosing the point of lift, check that the 
correct winch has been selected. If no other pick point 
options are available, the message, “No Other Pick 
Point Options” will be displayed.

TEST

SET

MAX

ERECTED JIB

TEST

SET

MAX

AUXILIARY HEAD

TEST

SET

MAX

WINCH

TEST

SET

MAX

POINT OF LIFT

W450520 0

7 2020

Summary of Contents for MicroGuard RCI 510

Page 1: ...MicroGuard RCI 510 Upgrade Rated Capacity Indicator System For Telescopic Boom Cranes Operation...

Page 2: ......

Page 3: ...rast 6 Counterweight 7 Outriggers 7 Tires and Rigging Travel 7 Stowing the Jib 7 Erecting the Jib 8 Auxiliary Head 8 Selecting the Winch 8 Setting the Parts of Line 9 Cancel Alarm Button 9 Reset Funct...

Page 4: ...MicroGuard 510 Upgrade ii W450520 07 2020...

Page 5: ...the extension of the boom A cable attached to the boom head provides a low current electrical path for the ATB signal Pressure Transducers Two pressure transducers measure the pressure in the boom ho...

Page 6: ...These alarms can be programmed for each job site and allow the operator to work in a defined area Boom Angle Sensor Boom angle is measured by means of a high accuracy potentiometer pendulum assembly...

Page 7: ...are defined below 2 1 3 4 5 6 8 7 9 1 Jibs Indicates the configuration of an erected jib 2 Aux Head Illuminates when the auxiliary head is fitted 3 Point Of Lift Switches between boom auxiliary head a...

Page 8: ...r Shows the load as a percentage of rated capacity As the load increases the meter level increases to represent the percentage of the rated capacity of the crane 6 Rated Capacity Displays the rated ca...

Page 9: ...gnostics 15 Input Select Select and enter calibration information 16 Operator Alarm Set Enables operator alarms When an alarm has been set the LED above this button will illuminate yellow mWarning You...

Page 10: ...r The screen is a reminder to read important documentation before proceeding with operation of the system Adjusting Brightness Contrast Immediately following self test and the start up screen the info...

Page 11: ...re than one tire option e g static creep etc the operator must select the tire configuration that corresponds to the tire chart to be used If the tire push button is pressed on a crane that does not h...

Page 12: ...ave an auxiliary head the message No Other Auxiliary Head Options will appear in the information screen Selecting the Winch For cranes with two winches always select the winch to be used for the lift...

Page 13: ...proximately five seconds to reset the relay and another beep will be heard confirming the override The override condition will remain in effect only as long as the cancel key is held When the cancel k...

Page 14: ...desired maximum length in this example 78 ft Press the Operator Alarm Button to access the Operator Alarm Screen Press the Max Height Button The display will read Max Height 78 ft The red warning ligh...

Page 15: ...m is activated when swinging to the right In this example the working arc is the smaller piece of the pie A left swing alarm is activated when swinging to the left A right swing alarm is activated whe...

Page 16: ...Press the keys adjacent to Left Swing and Right Swing so they show off Rotate the boom to the left swing point and press the key adjacent to Left Swing then press the key adjacent to Next to proceed...

Page 17: ...ress the key adjacent to Next to proceed Rotate the boom to the right swing point and press the key adjacent to Off Press the key adjacent to Finish to complete the routine TEST SET MAX TEST SET MAX T...

Page 18: ...E mWarning The Operator Defined Work Area Alarm Is a Warning Device All Functions Remain Operational When Entering The Operator Defined Exclusion Zone Safe Working Distance is the time it would take t...

Page 19: ...reached this will avoid having to pass through the exclusion zone This is the point to the right facing the exclusion zone to be defined Press the key adjacent to Right Point To deactivate the swing a...

Page 20: ...lsa Winch Group www dovertwg com As a leader in product innovation Greer Company is committed to the ongoing improvement of its equipment We reserve the right to make changes to our products without n...

Reviews: