1 Engineering Installation Preparation and Notice
1.1 Installation notice
Personnel and property safety are highly concerned during the entire installation process. Installation implementation must abide by
relevant national safety regulations to ensure personnel and property safety.
All personnel involved in the installation must attend safety education courses and pass corresponding safety examinations before
installation. Only qualified personnel can attend the installation. Relevant personnel must be held responsible for any violation of the
regulation.
1.2 Installation key points and importance
VRF air conditioning systems use refrigerant, instead of other agent, to directly evaporate to carry out the system heat. High level
of pipe cleanness and dryness is required in the system. Since various pipes need to be prepared and laid out onsite, carelessness or
maloperation during installation may leave impurities, water, or dust inside refrigerant pipes. If the design fails to meet the requirement,
various problems may occur in the system or even lead to system breakdown.
Problems that usually occur during installation are as follows:
No.
Installation Problem
Possible Consequence
1
Dust or impurities enter into the
refrigeration system.
Pipes are more likely to be blocked; air conditioning performance is reduced;
compressor wear is increased or even hinder the normal operation of the system and
burn the compressor.
2
welding.
Pipes are more likely to be blocked; air conditioning performance is reduced;
compressor wear is increased or even hinder the normal operation of the system and
burn the compressor.
3
The vacuum degree in the refrigerant pipe The refrigeration performance is reduced. The system fails to keep normal operation
due to frequent protection measures. When the problem getting serious, compressor
and other major components can be damaged.
4
Water enters into the refrigeration system.
with abnormal noise generated; failures may occur in the system due to ice plug.
5
materials and can also reduce the cooling performance.
6
Refrigerant pipe is blocked.
The cooling performance is reduced; in certain cases, it may cause long-term
compressor operating under overheat conditions; the lubricating effect can be
affected and the compressor may be burnt if impurities were mixed with the
lubricating oil.
7
Refrigerant pipe exceeds the limit.
harmful for long-term running of the system.
8
to the compressor.
9
The refrigerant pipe leaks.
of the air conditioner. Long-term operation under such circumstance may cause an
overheating compressor or even damage the compressor.
10
Water drainage from the condensate water
pipe is not smooth.
Residual water in IDUs can affect the normal operation of the system. The possible
water leakage can damage the IDU's decoration.
11
The ratio of slop for condensate water pipe
is incorrectly connected.
Reverse slop or inconsistent connection of condensate water pipe can hinder the
smooth drainage and cause leakage of the IDU.
12
The air channel will deform; vibration and noise occur during unit operating.
13
The guide vane of air channel is not
reasonably manufactured.
Uneven air quantity allocation reduces the overall performance of the air conditioner.
Summary of Contents for R410A
Page 1: ...Photovoltaic Direct driven VRF for North America R410A GC201610 1 ...
Page 3: ...1 Photovoltaic Direct driven VRF for North America PRODUCT PRODUCT ...
Page 15: ...13 for North America CONTROL CONTROL Photovoltaic Direct driven VRF ...
Page 38: ...36 Photovoltaic Direct driven VRF for North America INSTALLATION ...
Page 61: ...MAINTENANCE for North America Photovoltaic Direct driven VRF 59 ...
Page 65: ...63 for North America Photovoltaic Direct driven VRF 3 Discharge temperature protection ...
Page 90: ...JF00303127 ...