background image

Installation

332590A

7

Install Cellular Module

18. Use two locking nuts (5) to secure cellular 

module (1) to bracket (3). Orient module (1) on 
bracket so LED window (AA) is easily visible to 
operator when bracket is installed on Reactor. 

19. Loosen left side acorn nuts (AN) holding Reactor 

display to frame until display can be lifted enough to 
slide bracket between frame and display. See F

IG

. 7. 

NOTE: It is not necessary to completely remove the 
acorn nuts on the electric Reactor.

20. Slide bracket between display and frame so that 

bracket mounts to the behind the display with the 
LED status window (AA) visible to operator and the 
cable connector on the bottom. See F

IG

. 7.

21. Tighten acorn nuts (AN) to secure bracket in place. 

See F

IG

. 7. 

22. Connect 4-pin end of cable (4) to cellular module (1) 

connector. See F

IG

. 7. 

23. Route cellular module cable (4) to control box (D). 

Secure with wire ties (8) as needed.

24. Connect other end of cellular module cable (4) to 

control box (D) connector.

NOTICE

To prevent cracking the plastic shell of the cellular 
module (1), do not overtighten nuts (5) when install-
ing onto bracket (3).

5

1

3

AA

ti21689a

F

IG

. 7

ti21690a

D

D

Electric Reactor

Hydraulic Reactor

AN

1

3

5

AN

5

1

3

4

4

Summary of Contents for InSite 24T278

Page 1: ...temperature setpoint actual pressure pressure setpoint cycles and GPS location from a Reactor proportioner Not approved for use in explosive atmospheres or hazardous locations Model 24T278 Important S...

Page 2: ...Reac tor models Manual Description 312062 Hydraulic Reactor Operation 312063 Hydraulic Reactor Repair 312065 Electric Reactor Operation 312066 Electric Reactor Repair Reactor Model Part Numbers E 20...

Page 3: ...cables from control box 2 through split rubber sheet in top of cabinet NOTE Electric Reactor only When installing the control box in the following step pull wires through the split rub ber sheet in to...

Page 4: ...grounding wire G from control box into grounding terminal block 6 supplied with kit then tighten screw Y to secure wire 9 Install grounding terminal block 6 onto right end of DIN rail then tighten cen...

Page 5: ...Installation 332590A 5 FIG 1 Electric Reactor DIN Rail Style 1 FIG 2 Electric Reactor DIN Rail Style 2 FIG 3 Hydraulic Reactor DIN Rail Style 3 B C S F Z 6 G Y X B C S F X G Y 6 F S B C 6 Y X...

Page 6: ...install cover kit AA See FIG 5 NOTE The cap on the HEAT cable plug may prevent plug from being fully inserted into the temperature con trol module Press plug to the right then press plug the rest of...

Page 7: ...ween display and frame so that bracket mounts to the behind the display with the LED status window AA visible to operator and the cable connector on the bottom See FIG 7 21 Tighten acorn nuts AN to se...

Page 8: ...en LED on the Temperature Control Module will blink rapidly and the display will show E99 When the update is com plete the green light on the Temperature Control Mod ule will blink slowly and the disp...

Page 9: ...l number from the cel lular box below Verify Module Status To check the status of the cellular module locate the status LEDs on the module then refer to the following chart LED Status Description Gree...

Page 10: ...lled See Installation on page 3 Verify 12V at output of the power supply Make sure the M8 4 pin to M12 8 pin cable is installed between cel lular module and control box Has not identified GPS location...

Page 11: ...mocouple is not correctly installed on the hose or is broken See Reactor repair manual Pressure data not displayed on website 4 pin connector is not plugged into the correct terminal on the tempera tu...

Page 12: ...2e SPACER nylon 1 2f NUT 4 40 1 2g LABEL 1 2h 127189 CONVERTER 1 2i 127188 POWER SUPPLY 12V 1 3 16V506 BRACKET mounting 1 4 24T050 CABLE M8 4 pin Female to M12 8 pin Male 1 5 meters 1 5 NUT locking 8...

Page 13: ...Weight 2 3 lb 1 0 kg Cellular Module Weight 0 5 lb 0 2 kg Voltage into Control Box 100 240VAC 50 60 Hz Operating Temperature 22 to 167 F 30 to 75 C Storage Temperature 40 to 185 F 40 to 85 C Ambient...

Page 14: ...ipment does not disclose any defect in material or workmanship repairs will be made at a reasonable charge which charges may include the costs of parts labor and transportation THIS WARRANTY IS EXCLUS...

Reviews: