14
1. Crimping with grounding terminals at both ends.
2. Connect the ground cables to the Battery Module and the
PCU
.
Connect the PE cable first before installing the equipment. Disconnect the PE cable
before dismantling the equipment.
The cross-sectional area of the PE cable conductor: 5mm
2
. The cable should meet
standards for outdoor use.
The drawing force of the cable after crimping should be at least 400N.
All Battery Modules and power control units should be grounded separately.
L1
L2=L1+1~2mm
5.4.2 Grounding Cable Connection
3.5 N·M
M5
3.5 N·M