WARNING:
DISCONNECT ELECTRICAL POWER SUPPLY AND PLACE A
TAG AT THE DISCONNECT SWITCH TO INDICATE THAT YOU ARE
WORKING ON THE CIRCUIT.
Some machines may have more than one electrical power supply. All supplies
must
be disconnected
.
Motor(s)
Connect a permanent electrical power supply to the terminal block in the control box.
Three-phase motor rotate the impeller in the direction of the arrow found on the
pump housing of the motor pump unit, and the drive motor must rotate clockwise
when viewed from the output shaft end. Before placing the machine into service, a
check must be made to verify correct rotation. Only one motor needs to be checked
as the machine is wired at the time of manufacture so that all motors will rotate the
same direction.
If the impeller does not rotate in the direction of the arrow, DISCONNECT POWER
SUPPLY to the machine and interchange any two power supply leads at the control
box terminal block. Or machine with a circuit breaker, reverse any two leads at the
incoming power supply block in the circuit breaker (three-phase only). Start the
machine momentarily and verify proper direction of rotation.
WARNING:
Circuit breakers for booster heater have been switched off before
machine leaving factory to avoid dry operation of the booster elements.
SWITCH
ON CIRCUIT ONLY AFTER THE FOLLOWING PROCEDURE.
Position and
level the dishwasher; connect electrical power, water inlet and drain pipe. Turn on
the power switch; solenoid valve is activated to fill the machine. When the tanks are
full, Both circuit breakers for booster heater can be switched on now .
Failure to
follow this procedure can result in machine manage.
OPERATION
PREPARATION
Put the dishwasher strainer pans and strainer basket into position in each tank. Put
the final rinse screen over the final rinse catch pan.
Hang curtains on open hooks provides to your machine.
Be sure long & short
curtains are located correctly.