LRR 1-52, LRR 1-53, URB 55 - USA - Installation & Operating Manual -
850703-00
Configuring the conductivity controller
Setting the control parameters
Parameter
Control deviation
Control valve
Proportional
band
Pb
> larger Large remaining deviation
Reacts slowly
< smaller Small remaining deviation
Reacts quickly and may open/close
continually
Example:
Measuring range 0 to 3000 ppm (0 to 6000 µS/cm)
Set point SP = 1500 ppm (3000 µS/cm)
Proportional band Pb = +/- 20% of set point = +/- 300 ppm (600 µS/cm)
With the measuring range and set point mentioned above, the proportional band
is then +/- 300 ppm (600 µS/cm) or in the range from 1200 ppm (2400 µS/cm)
to 1800 ppm (3600 µS/cm).
Reset time
Ti
> larger Slow correction of deviations
Reacts quickly
< smaller
Fast correction of deviations, the control
loop may tend to overshoot
Reacts slowly
Dead
band
> larger
Correction of deviations starts with a
delay
In this range, the manipulated variable
does not change.
Only reacts when the control
deviation is larger than the “dead
band”.
< smaller Correction of deviations starts rapidly
Valve runtime
Tt
Establish the real valve runtime, e.g.,
from “Closed” to “Open” (0 - 100%).
Operating
position
Defined opening of the continuous
blowdown valve. Closes on standby.
Fig. 23
Open the control parameter
screen.
Guide to setting control parameters
Summary of Contents for LRR 1-52
Page 69: ...69 LRR 1 52 LRR 1 53 URB 55 USA Installation Operating Manual 850703 00 For your notes ...
Page 70: ...70 LRR 1 52 LRR 1 53 URB 55 USA Installation Operating Manual 850703 00 For your notes ...
Page 71: ...71 LRR 1 52 LRR 1 53 URB 55 USA Installation Operating Manual 850703 00 For your notes ...