Installation
ATTENTION
Incorrect installation can lead to malfunctions in the system or the conductivity
electrode.
■
■
Inspect the sealing surfaces of tank threaded couplings or flange covers to ensure they are
perfectly machined, see Fig. 10.
■
■
Take care not to bend the electrode rods during installation!
■
■
Do not subject measuring electrodes to hard impacts during installation.
■
■
Do
not
install the body
A
or sheath
E
of the measuring electrode in the boiler thermal
insulation!
■
■
Pay attention to the mounting dimensions of the conductivity electrode, see installation
examples on pages 31 to 34.
■
■
Check the boiler connection and flange during the preliminary boiler inspection.
■
■
Tighten to the specified torques.
Additional notes for installation
ATTENTION
If the electrode is not fully immersed in the fluid, measurement results may be false
and there is a risk to plant safety.
■
■
Install the conductivity electrode in such a way that the measuring electrodes are always
fully immersed in the fluid.
■
■
As far as possible, always install the conductivity electrode below the admissible LW mark.
Ground points (metal objects) between the boiler wall and the electrode have
an adverse effect on measurement. False measurement results are a risk to plant safety.
Therefore, always adhere to the distances stated below.
LRGT 16-3, LRGT 17-3
■
■
Provide spacing of approx. 30 mm between the lower end of the measuring tube and the
boiler wall, the smoke tubes and any other metallic fittings, and the low water level (LW).
■
■
Do not shorten the measuring electrode or measuring tube.
LRGT 16-4
■
■
Provide spacing of approx. 60 mm between the lower end of the measuring tube and the
boiler wall, the smoke tubes and any other metallic fittings, and the low water level (LW).