1.2M Ku-BAND Rx/Tx SERIES 1123
6
1.6 FOUNDATION
INTERFACE
The required interface from the foundation to the mount is 2-1/2" schedule 40
pipe (2.88" O.D.). A suggested in-ground foundation is shown in Figure 1.
NOTES:
1.
2 1/2” schedule 40 pipe should conform with ASTM A53.
2.
All concrete should conform to building code standards and have a
minimum compressive strength of 3000 PSI at 28 days. (Per ACI-318-77)
3.
Soil bearing capacity should be no less than 2000 PSF.
4.
Concrete should be poured against undisturbed soil.
5.
Allow concrete 24 hours set time before installation of antenna.
6.
The antenna should be properly grounded to meet applicable local codes.
7.
Minimum depth as shown or extend to local frost line.
8.
Foundation meets the design requirements as set forth by the uniform building code.
(1982 edition)
(GENERAL DYNAMICS DOES NOT REPRESENT OR WARRANT THAT ANY PARTICULAR DESIGN
OR SIZE OF FOUNDATION IS APPROPRIATE FOR ANY LOCALITY OR EARTH STATION
INSTALLATION.)
30.0
30.0
SEE NOTE #7
45
12.0
SECTION A - A
A
A
2 1/2” SCH 40 PIPE
(2.88 O.D.)
Figure 1