Following transfer switch installation and interconnection, inspect
the entire installation carefully. A competent, qualified electrician
should inspect it. The installation should comply strictly with all
applicable codes, standards, and regulations. When absolutely
certain the installation is proper and correct, complete a functional
test of the system. Perform functional tests in the exact order pre-
sented in this manual, or the switch could be damaged.
IMPORTANT:
Before proceeding with functional tests, read and
make sure all instructions and information in this section are
understood. Also read the information and instructions of labels
and decals affixed to the switch. Note any options or accessories
that might be installed and review their operation.
3.2 MANUAL
OPERATION
DANGER
Do NOT manually transfer under load.
Disconnect transfer switch from all power sourc-
es by approved means, such as a main circuit
breaker(s).
A manual HANDLE is shipped with the transfer switch. Manual
operation must be checked BEFORE the transfer switch is operated
electrically. To check manual operation, proceed as follows:
1. In the transfer switch enclosure, set the Maintenance
Disconnect switch to MANUAL. This prevents the generator
from starting automatically as soon as the UTILITY power
source is turn OFF.
2. If so equipped, turn the generator’s AUTO/OFF/ MANUAL
switch to OFF.
3. Turn OFF both NORMAL and STANDBY power supplies to the
transfer switch, with whatever means provided (such as the
main line circuit breaker(s)).
4. Note position of transfer mechanism main contacts by
observing display windows in “A” and “B” in Figure 3.1 as
follows:
Window “A” ON, Window “B” OFF - LOAD terminals (T1, T2,
•
T3) are connected to NORMAL terminals (N1, N2, N3).
Window “A” OFF, Window “B” ON - LOAD terminals (T1, T2,
•
T3) are connected to STANDBY terminals (E1, E2, E3).
Do not use excessive force when operating the
transfer switch manually or the manual handle
could be damaged.
Section 3 — Operation
HTS “Wn” Type Transfer Switch
Figure 3.1 — Actuating Transfer Switch
Summary of Contents for HTS Wn
Page 16: ...14 Section 5 Notes HTS Wn Type Transfer Switch 14...
Page 17: ...15 Section 5 Notes HTS Wn Type Transfer Switch 15 15...
Page 18: ...16 Section 6 Mounting Dimensions 600 1000A NEMA 12 Drawing No 0F6963 D...
Page 19: ...17 Section 6 Mounting Dimensions 600 1000A NEMA 12 Drawing No 0F6963 D...
Page 20: ...18 Section 6 Mounting Dimensions 600 1000A NEMA 3R Drawing No 0F7314 D...
Page 21: ...19 Section 6 Mounting Dimensions 600 1000A NEMA 3R Drawing No 0F7314 D...
Page 22: ...20 Section 6 Mounting Dimensions 1200 1600A NEMA 12 Drawing No 0F7520 C...
Page 23: ...21 Section 6 Mounting Dimensions 1200 1600A NEMA 12 Drawing No 0F7520 C...
Page 24: ...22 Section 6 Mounting Dimensions 1200 1600A NEMA 3R Drawing No 0F7521 C...
Page 25: ...23 Section 6 Mounting Dimensions 1200 1600A NEMA 3R Drawing No 0F7521 C...
Page 26: ...24 Section 6 Mounting Dimensions 2000 2600A NEMA 12 Drawing No 0F8944 C...
Page 27: ...25 Section 6 Mounting Dimensions 2000 2600A NEMA 12 Drawing No 0F8944 C...
Page 28: ...26 Section 6 Mounting Dimensions 2000 2600A NEMA 3R Drawing No 0F8945 C...
Page 29: ...27 Section 6 Mounting Dimensions 2000 2600A NEMA 3R Drawing No 0F8945 C...
Page 30: ...28 Section 7 Wiring Diagrams Electrical Schematics Wiring Diagram 208 240V Drawing No 0F7043 B...
Page 31: ...29 Section 7 Wiring Diagrams Electrical Schematics Wiring Diagram 208 240V Drawing No 0F7043 B...
Page 34: ...32 Section 7 Wiring Diagrams Electrical Schematics Wiring Diagram 480 600V Drawing No 0F7045 B...
Page 35: ...33 Section 7 Wiring Diagrams Electrical Schematics Wiring Diagram 480 600V Drawing No 0F7045 B...