Rev. 00 01/22
PH300
Start-up
•
19
Start-up inspection
No.
Inspection
✓
1
All screw connections are tight.
2
Power levels are correct. See chapter "Filling the
powder hopper" on page 17.
3
Fluidization air is set correctly.
4
The interior of the powder hopper is clean. See chapter
"Cleaning the interior of the powder hopper" on page
26.
5
The operating manual is stored with the machine close
to the work station.
6
The operator has been told that he is responsible for
instructing the personnel.
7
Assembly and installation have been concluded in
accordance with the operating manual.
8
Electrical and mechanical safety equipment is in perfect
working order.