V12/19
iONstream 4.0
Mechanical Installation
•
19
Mechanical Installation
Determining Locations for Neutralizing Bars
WARNING
Explosion hazard
► If the system is installed in a potentially explosive zone, the
position of the neutralizing bar must be selected in such a way
that the substrate is discharged and does not pose a risk of
ignition.
Attach the neutralizing bar to the desired position, as shown in
Fig. 2
, for
neutralization of web spans and other applications where the distance
between the bar and the material does not vary.
fig. 2
A:
Distance to roller must be greater than 1x diameter of the roller.
*
Dimensions in this image are based on experience and may differ
from case to case. Adequate ionization efficiency must be
demonstrated for the particular application by measurement.
The bar should not be closer than 80 - 300 mm (6 kV), 300 - 600
mm (12 kV) or 600 - 1000 mm (18 kV) to the roller.
A:
> 1 x d
d
iONstream
6 kV: 80 ~ 300 mm*
12 kV: 300 ~ 600 mm*
18 kV: 600 ~ 1000 mm*
6 kV
12 kV
18 kV