background image

 

Figure 4. Installing a carriage bolt [14] and antiturn clip [4] 

into the interior. 

Figure 4. Installation d’un boulon de carrosserie [14] et d’un 

clip immobilisé [4] dans l’intérieur. 

For the following steps, Figure 5 illustrates the possible bus 
strap configurations. 

4.Three-phase installations.

 Use the following procedure for 

all three-phase installations (kit AMCB6FGB). 

4a. Install carriage bolt assemblies.

 Position the 

carriage bolt [14] and antiturn clip [4] assemblies as 
shown in Figures 6 and 7.  

 

Figure 7. Carriage bolt and antiturn clip installation for three-

phase connections, isometric view. 

Figure 7. Vue isométrique de l’installation d’un boulon de 

carrosserie et d’un clip immobilisé pour des connexions trois-

phases. 

4b. Install straps.

 Place the FG frame straps [5, 6] over 

the carriage bolts and antiturn clips, as shown in 
Figures 8 and 9. Place conical washers [7] on the bolts 
and secure with nuts [11].  A phase strap assembly is 
10083795G1 and C phase is 10083795G9.  Insure that 
these are positioned on the correct bus bars,  Leave 
the connections finger tight. Go to step 6 to install the 
mounting brackets. 

G9

 

Figure 9. Installing the straps for three-phase connections, 

isometric view. 

Figure 9. Vue isométrique de l’installation des brides pour des 

connexions trois-phases. 

La Figure 5 illustre les configurations possibles de courroies de 
barre omnibus pour les étapes suivantes. 

 4. 

Installations 

trois-phases.

 Utiliser la procédure suivante 

pour toutes les installations trois-phases (kit 
AMCB6FGB). 

4a.  Installer les assemblages de boulon de carrosserie.

 

Positionner les assemblages de boulon de carrosserie 
[14] et de clips immobilisés [4] tel que montré aux 
Figures 6 et 7. 

 

Figure 6. Carriage bolt and antiturn clip installation for three-

phase connections. 

Figure 6. Installation d’un boulon de carrosserie et d’un clip 

immobilisé pour des connexions trois-phases. 

4b.  Installer les brides.

 Placer les brides de cadre FG [5, 

6] par-dessus les boulons de carrosserie et les clips 
immobilisés, tel que montré aux Figures 8 et 9. Placer 
les rondelles cuvettes [7] sur les boulons et fixer avec 
des écrous [11]. Serrer les connexions au doigt. Aller 
à l’étape 6 pour installer les supports de fixation. 

 

Figure 8. Installing the straps for three-phase connections. 

Figure 8. Installer les brides pour des connexions trois-phases. 

3

 

Summary of Contents for Spectra Series AMCB6FGB

Page 1: ...ue AMCB6FGB et AMCB4FGB Ces kits sont pour utilisation de disjoncteurs de types FGH FGL FGN et FGP Utiliser le kit de couvercle de disjoncteur de numéro de catalogue AFP4FGD Installation AVERTISSEMENT Danger de choc électrique ou de blessure Mettre le courant en avant du panneau de distribution ou du tableau de contrôle à Off avant de travailler à l intérieur de l équipement ou d en retirer toute ...

Page 2: ...ste des pièces pour les kits AMCB4FGB et AMCB6FGB 2 Locate the side of the interior with a 2 75 inch reference distance The circuit breaker straps are mounted on the side of the panel interior bus at which the distance from the vertical bus face to the inner face of the bus support rail is 2 75 inches as indicated in Figure 2 3 Assemble antiturn clips onto carriage bolts Slide an antiturn clip 4 o...

Page 3: ...ight Go to step 6 to install the mounting brackets G9 Figure 9 Installing the straps for three phase connections isometric view Figure 9 Vue isométrique de l installation des brides pour des connexions trois phases La Figure 5 illustre les configurations possibles de courroies de barre omnibus pour les étapes suivantes 4 Installations trois phases Utiliser la procédure suivante pour toutes les ins...

Page 4: ...ble bus strap combinations Figure 5 Combinaisons possibles de brides de barre omnibus 5 Two pole installations Use the following procedure for all two pole installations kit AMCB4FGB For installations using phases A and B continue with step 5a For installations using phases A and C go to step 5c For installations using phases B and C go to step 5e 5 Installations deux pôles Utiliser la procédure s...

Page 5: ...lages de boulon de carrosserie sur des phases A et B Positionner les assemblages de boulon de carrosserie 14 et de clip immobilisé 4 tel que montré aux Figures 10 et 11 Figure 11 Installing carriage bolt assemblies on phases A and B isometric view Figure 11 Vue isométrique d assemblage de boulons de carrosserie sur des phases A et B 5b Installer les brides sur des phases A et B Placer les brides d...

Page 6: ...A et C Placer les brides de cadre FG 5 sur les boulons de carrosserie et les clips immobilisés tel que montré aux Figures 16 et 17 Placer les rondelles cuvettes 7 sur les boulons et fixer avec des écrous 11 Serrer les connexions à la main Aller à l étape 6 pour installer les supports de fixation Figure 17 Installing straps on phases A and C isometric view Figure 17 Vue isométrique de l installatio...

Page 7: ...rail latéral du panneau avec des vis auto taraudeuses 1 tel que montré à la Figure 22 Serrer les vis à 30 po lb 7 Installer les disjoncteurs Positionner la barrière par dessus le support de fixation tel que montré à la Figure 23 Positionner les disjoncteurs de manière à ce que les terminaux du côté ligne ou On reposent sur les blocs de contact sous jacents des brides et que les côtés opposés soien...

Page 8: ...l autre dérivation laissée ouverte pour future utilisation En ce cas isoler les surfaces exposées des blocs de contact des brides dans la dérivation inutilisée Couvrir les surfaces de contact avec deux couches de ruban thermoplastique reconnu UL 105 C OANZ2 tel que Permacel P 30 105 ou 3M 66R afin d obtenir une épaisseur minimale d isolation de 0 013 pouce These instructions do not cover all detai...